Quantative Analysis using school generated .xls file and provided table EXCEL/ACCOUNTING/MATH

profileEskimoMarine
task4rubric.pdf

6/29/2015 TaskStream

https://w.taskstream.com//RubricWizard/RubricPrintViewWithSession/PrintView?legacySessionId=7bx4Y6M6HYdD4gX90fF&encLegacyRubricId=aiz7enzgfx… 1/3

QAT Task 4 (1014)

value: 0.00 value: 1.00 value: 2.00 Score/Level

Articulation of Response (clarity, organization, mechanics)

The candidate provides unsatisfactory articulation of response.

The candidate provides weak articulation of response.

The candidate provides adequate articulation of response.

 

A1. Expected Completion Time

The candidate does not accurately determine the expected completion time for any project activities.

The candidate accurately determines the expected completion time for 1–8 of the project activities.

The candidate accurately determines the expected completion time for each of the 9 project activities.

 

A1a. Answers for Part A1

The candidate does not provide all answers for part A1 in Table 1.1.

The candidate provides, with insufficient support, all answers for part A1 in Table 1.1.

The candidate provides, with sufficient support, all answers for part A1 in Table 1.1.

 

A2. Variance The candidate does not accurately determine the variance for any project activities.

The candidate accurately determines the variance for 1–8 of the project activities.

The candidate accurately determines the variance for each of the 9 project activities.

 

A2a. Answers for Part A2

The candidate does not provide all answers for part A2 in Table 1.1.

The candidate provides, with insufficient support, all answers for part A2 in Table 1.1.

The candidate provides, with sufficient support, all answers for part A2 in Table 1.1.

 

A3. PERT Chart The candidate does not provide a PERT chart showing the network diagram with the activities and their expected times.

Not applicable. The candidate provides a PERT chart showing the network diagram with the activities and their expected times.

 

A3a. Critical Path The candidate does not accurately identify the critical path.

Not applicable. The candidate accurately identifies the critical path.

 

A4a. Expected Duration

The candidate does not accurately determine the expected duration of the entire project.

The candidate accurately determines, with insufficient support, the expected duration of the entire project.

The candidate accurately determines, with sufficient support, the expected duration of the entire project.

 

A4b. Activity E Slack The candidate does not accurately determine the slack

The candidate accurately determines, with

The candidate accurately determines, with

 

Export to Word

6/29/2015 TaskStream

https://w.taskstream.com//RubricWizard/RubricPrintViewWithSession/PrintView?legacySessionId=7bx4Y6M6HYdD4gX90fF&encLegacyRubricId=aiz7enzgfx… 2/3

for project Activity E. insufficient support, the slack for project Activity E.

sufficient support, the slack for project Activity E.

A4c. Activity C Slack The candidate does not accurately determine the slack for project Activity C.

The candidate accurately determines, with insufficient support, the slack for project Activity C.

The candidate accurately determines, with sufficient support, the slack for project Activity C.

 

A4d. Activity F Start The candidate does not accurately determine the earliest week project Activity F is scheduled to start.

The candidate accurately determines, with insufficient support, the earliest week project Activity F is scheduled to start.

The candidate accurately determines, with sufficient support, the earliest week project Activity F is scheduled to start.

 

A4e. Activity G Finish The candidate does not accurately determine the latest week project Activity G is scheduled to finish.

The candidate accurately determines, with insufficient support, the latest week project Activity G is scheduled to finish.

The candidate accurately determines, with sufficient support, the latest week project Activity G is scheduled to finish.

 

A5. Probability of Completion

The candidate does not accurately determine the probability of completing this project in time for the product launch in 48 weeks.

The candidate accurately determines, with insufficient support, the probability of completing this project in time for the product launch in 48 weeks.

The candidate accurately determines, with sufficient support, the probability of completing this project in time for the product launch in 48 weeks.

 

B1. Maximum Reduction

The candidate does not accurately determine the maximum reduction in time for any of the project activities.

The candidate accurately determines the maximum reduction in time for 1–9 of the project activities.

The candidate accurately determines the maximum reduction in time for each of the 10 project activities.

 

B1a. Answers for B1 The candidate does not provide all answers for part B1 in Table 1.2.

The candidate provides, with insufficient support, all answers for part B1 in Table 1.2.

The candidate provides, with sufficient support, all answers for part B1 in Table 1.2.

 

B2. Crash Cost The candidate does not accurately determine the crash cost per week for any of the project activities.

The candidate accurately determines the crash cost per week for 1–9 of the project activities.

The candidate accurately determines the crash cost per week for each of the 10 project activities.

 

B2a. Answers for B2 The candidate does not provide all answers for part B2 in Table 1.2.

The candidate provides, with insufficient support, all answers for part B2 in Table 1.2.

The candidate provides, with sufficient support, all answers for part B2 in Table 1.2.

 

6/29/2015 TaskStream

https://w.taskstream.com//RubricWizard/RubricPrintViewWithSession/PrintView?legacySessionId=7bx4Y6M6HYdD4gX90fF&encLegacyRubricId=aiz7enzgfx… 3/3

C1. Activities to be Crashed

The candidate does not accurately identify the activities, considering all paths, to be crashed to meet the given criteria.

Not applicable. The candidate accurately identifies the activities, considering all paths, to be crashed to meet the given criteria.

 

C2. Number of Weeks The candidate does not accurately determine the number of weeks each of the activities identified in part C1 should be crashed.

Not applicable. The candidate accurately determines the number of weeks each of the activities identified in part C1 should be crashed.

 

C3. Sum of Individual Costs

The candidate does not accurately determine the sum of the individual costs of crashing each activity identified in part C1.

Not applicable. The candidate accurately determines the sum of the individual costs of crashing each activity identified in part C1.

 

D. Sources When the candidate uses sources, the candidate does not provide in­text citations and references.

When the candidate uses sources, the candidate provides appropriate in­text citations and references with major deviations from APA style.

When the candidate uses sources, the candidate provides appropriate in­text citations and references accurately or with only minor deviations from APA style.