Operations and Supply Chain Management

MGMT 3306

Lecture 02

Instructor: Dr. Yan Qin

Outline

Project Management

What is Project Management?

Three types of projects

Work Breakdown Structure (WBS)

Project Management Techniques: PERT and CPM

Cost-Time Trade-Offs and Project Crashing

A Critique of PERT and CPM

2

Project Management

A project is a series of related jobs usually directed toward some major output and requiring a significant period of time to perform.

Project Management is the planning, scheduling, and controlling of resources to meet the technical, cost, and time constraints of the project.

3

Examples of Projects

Building Construction

Research Project

Three Phases of Project Management

The management of projects involves three phases:

Planning - goal setting, defining the project, team organization

Scheduling - relates people, money, and supplies to specific activities and activities to each other

Controlling - monitors resources, costs, quality, and budgets; revises plans and shifts resources to meet time and cost demands

Project Planning

Figure 3.1

Before Start of project During

project Timeline project

Project Scheduling

Figure 3.1

Before Start of project During

project Timeline project

Project Controlling

Figure 3.1

Before Start of project During

project Timeline project

Project Planning, Scheduling, and Controlling

Figure 3.1

Before Start of project During

project Timeline project

Project Organizations

There are three types of project based on the organizational structures used to tie the project to the parent firm:

Pure project: A self-contained team works full time on a project;

Functional project: A project housed within a functional division.

Matrix project: A project that uses people from different functional areas.

The project manager decides what tasks to complete and when;

The functional managers control which people and technologies to be used in the project.

10

Example of Matrix Project

Marketing Operations Engineering Finance

Project 1

Project 2

Project 3

Project 4

Work Breakdown Structure (WBS)

Work Breakdown Structure (WBS): defines the hierarchy of project tasks, subtasks, and work packages

Program

Project 1

Project 2

Task 1.1

Subtask 1.1.1

Work Package 1.1.1.1

Level

1

2

3

4

Task 1.2

Subtask 1.1.2

Work Package 1.1.1.2

Task is a further subdivision of a project, usually shorter than several months.

Work package is a group of activities combined to be assignable to a single organizational unit, usually an individual.

12

Example: WBS – Large Optical Scanner Design

13

Purposes of Project Scheduling

Shows the relationship of each activity to others and to the whole project

Identifies the precedence relationships among activities

Encourages the setting of realistic time and cost estimates for each activity

Helps make better use of people, money, and material resources by identifying critical bottlenecks in the project

Project Management Techniques

Gantt chart

Critical Path Method (CPM)

Program Evaluation and Review Technique (PERT)

Gantt Chart

Charts are useful because their visual presentation is easily understood.

Gantt chart: a bar chart showing both the amount of time involved and the sequence in which activities can be performed

16

PERT and CPM

Both PERT and CPM are network techniques developed in 1950’s, which consider the inter-dependency among project activities.

CPM by DuPont for chemical plants (1957): A project management technique that uses only one time factor per activity. (Activity times are assumed to be certain.)

PERT by Booz, Allen & Hamilton with the U.S. Navy, for Polaris missile (1958): A technique that uses three time estimates for each activity. (Activities times are assumed to be uncertain.)

Questions PERT and CPM can answer

When will the entire project be completed?

What are the critical activities or tasks in the project?

Which are the noncritical activities?

What is the probability the project will be completed by a specific date?

Is the project on schedule, behind schedule, or ahead of schedule?

Is the money spent equal to, less than, or greater than the budget?

If the project must be finished in a shorter time, what is the way to accomplish this at least cost?

PERT and CPM: 6 Steps

Both PERT and CPM follow six basic steps:

Define the project and prepare the work breakdown structure

Develop relationships among the activities - decide which activities must precede and which must follow others

Draw the network connecting all of the activities

Assign time and/or cost estimates to each activity

Compute the longest time path through the network – this is called the critical path

Use the network to help plan, schedule, monitor, and control the project

Step 3: Draw a project network

A project network is a diagram of all the activities and the precedence relationships between the activities in a project.

There are two approaches for drawing a project network:

Activity-on-Node (AON): A network diagram in which nodes represent activities.

Activity-on-Arrow (AOA): A network diagram in which arrows represent activities.

AON Vs. AOA

Activity on Activity Activity on

Node (AON) Meaning Arrow (AOA)

A comes before B, which comes before C.

(a)

A

B

C

B

A

C

A and B must both be completed before C can start.

(b)

A

C

C

B

A

B

B and C cannot begin until A is completed.

(c)

B

A

C

A

B

C

AON Vs. AOA

Activity on Activity Activity on

Node (AON) Meaning Arrow (AOA)

C and D cannot begin until both A and B are completed.

(d)

A

B

C

D

B

A

C

D

C cannot begin until both A and B are completed; D cannot begin until B is completed. A dummy activity is introduced in AOA.

(e)

C

A

B

D

Dummy activity

A

B

C

D

AON Vs. AOA

Activity on Activity Activity on

Node (AON) Meaning Arrow (AOA)

B and C cannot begin until A is completed. D cannot begin until both B and C are completed. A dummy activity is again introduced in AOA.

(f)

A

C

D

B

A

B

C

D

Dummy activity

AON Vs. AOA

The AOA approach sometimes needs the addition of a dummy activity, represented by a dashed line, to clarify relationships.

A dummy activity consumes no time or resources, but is required in AOA when

A network has two activities with identical starting or ending events; or

Two or more activities follow some, but not all, “preceding” activities.

We will focus on AON in this class.

AON Example: Milwaukee Paper

Activity Description Immediate Predecessors
A Build internal components
B Modify roof and floor
C Construct collection stack A
D Pour concrete and install frame A, B
E Build high-temperature burner C
F Install pollution control system C
G Install air pollution device D, E
H Inspect and test F, G

Table 3.1

Given the following activities and precedence relationships in a project, draw an AON network representing the project.

AON Example: Project Network

A

Start

B

Start Activity

Activity A

(Build Internal Components)

Activity B

(Modify Roof and Floor)

We add a dummy activity called “Start” to serve as the unique starting activity of the project since we have more than one original starting activity (A and B) in this example.

AON Example: Project Network

C

D

A

Start

B

Activity A Precedes Activity C

Activities A and B Precede Activity D

We now add activity C and activity D to the network. Node C represents activity C and Node D represents activity D.

Note that arrows indicate precedence relationships between different activities in AON.

AON Example: Project Network

G

E

F

H

C

A

Start

D

B

Arrows Show Precedence Relationships

We will now look at Step 4

Both PERT and CPM follow six basic steps:

Define the project and prepare the work breakdown structure

Develop relationships among the activities - decide which activities must precede and which must follow others

Draw the network connecting all of the activities

Assign time and/or cost estimates to each activity

Compute the longest time path through the network – this is called the critical path

Use the network to help plan, schedule, monitor, and control the project

Step 4: Determine project schedule

To determine project schedule, we calculate two distinct starting and ending times for each activity.

Earliest start (ES): earliest time at which an activity can start, assuming all predecessors have been completed.

Earliest finish (EF): earliest time at which an activity can be finished

Latest start (LS): latest time at which an activity can start so as to not delay the completion time of the entire project

Latest finish (LF): latest time by which an activity has to be finished so as to not delay the completion time of the entire project

30

A node symbol with times

A

Activity Name or Symbol

Earliest Start

ES

Earliest Finish

EF

Latest Start

LS

Latest Finish

LF

Activity Duration

2

Forward Pass

ES and EF are determined using Forward Pass.

In the forward pass, we begin with the starting node and work forward.

Earliest Start Time Rule:

If an activity has only a single immediate predecessor, its ES equals the EF of the predecessor

If an activity has multiple immediate predecessors, its ES is the maximum of all the EF values of its predecessors

ES = Max {EF of all immediate predecessors}

Forward Pass

Earliest Finish Time Rule:

The earliest finish time (EF) of an activity is the sum of its earliest start time (ES) and its activity time

Start

0

0

ES

0

EF = ES + Activity time

Take the Start node in the previous Milwaukee problem for example:

Forward Pass

Here are the ES and EF of Node A in the previous Milwaukee example:

Start

0

0

0

A

2

2

EF of A = ES of A + 2

0

ES of A

Forward Pass

E

4

F

3

G

5

H

2

4

8

13

15

4

8

13

7

D

4

3

7

C

2

2

4

B

3

0

3

Start

0

0

0

A

2

2

0

Here are the ESs and EFs of all the activities in the previous Milwaukee example:

Backward Pass

In backward pass, we begin with the last event and work backwards.

Latest Finish Time Rule:

If an activity is an immediate predecessor for just a single activity, its LF equals the LS of the activity that immediately follows it

If an activity is an immediate predecessor to more than one activity, its LF is the minimum of all LS values of all activities that immediately follow it

LF = Min {LS of all immediate following activities}

Backward Pass

Latest Start Time Rule:

The latest start time (LS) of an activity is the difference of its latest finish time (LF) and its activity time

LS = LF – Activity time

Milwaukee Example: LS/LF

E

4

F

3

G

5

H

2

4

8

13

15

4

8

13

7

D

4

3

7

C

2

2

4

B

3

0

3

Start

0

0

0

A

2

2

0

LF = EF of Project

15

13

LS = LF – Activity time

We start from the ending node and work backward.

Milwaukee Example: LS/LF

E

4

F

3

G

5

H

2

4

8

13

15

4

8

13

7

13

15

D

4

3

7

C

2

2

4

B

3

0

3

Start

0

0

0

A

2

2

0

LF = Min(LS of following activity)

10

13

LF of Node F = LS of Node H since Node H is the only node following Node F.

Milwaukee Example: LS/LF

E

4

F

3

G

5

H

2

4

8

13

15

4

8

13

7

13

15

10

13

8

13

4

8

D

4

3

7

C

2

2

4

B

3

0

3

Start

0

0

0

A

2

2

0

LF = Min(4, 10)

4

2

There are two nodes, Node E and Node F, following Node C.

Milwaukee Example: LS/LF

E

4

F

3

G

5

H

2

4

8

13

15

4

8

13

7

13

15

10

13

8

13

4

8

D

4

3

7

C

2

2

4

B

3

0

3

Start

0

0

0

A

2

2

0

4

2

8

4

2

0

4

1

0

0

Project network with all the ES/EF and LS/LF.

We will now look at Step 5

Both PERT and CPM follow six basic steps:

Define the project and prepare the work breakdown structure

Develop relationships among the activities - decide which activities must precede and which must follow others

Draw the network connecting all of the activities

Assign time and/or cost estimates to each activity

Compute the longest time path through the network – this is called the critical path

Use the network to help plan, schedule, monitor, and control the project

Step 5: Determine Critical Path

The critical path is the longest path through the network.

The critical path is the shortest time in which the project can be completed.

Any delay in critical path activities delays the project.

Critical path activities have no slack time.

So in order to find the critical path(s), we need to first calculate the slack times of each activity and identify the activities with zero slack time.

Notes – Critical path and ES EL

Any sequence of activities between a project’s start and finish is a path.

The critical path is just the path that takes the longest time to complete.

There can be more than one critical paths.

An activity can be started at ES, LS, or any time between ES and LS.

Notes – Slack times

Activity slack is the maximum length of time an activity can be delayed without delaying the entire project.

Activities on the critical path have zero slack.

Activity slack can be calculated in two ways:

Slack = LS – ES OR

Slack = LF – EF

Example: Milwaukee

We have calculated the ES/EF, LS/LF times for the activities in the Milwaukee example. Now we would like to determine the critical path of the project.

Earliest Earliest Latest Latest On Start Finish Start Finish Slack Critical Activity ES EF LS LF LS – ES Path?

A 0 2 0 2 0 Yes

B 0 3 1 4 1 No

C 2 4 2 4 0 Yes

D 3 7 4 8 1 No

E 4 8 4 8 0 Yes

F 4 7 10 13 6 No

G 8 13 8 13 0 Yes

H 13 15 13 15 0 Yes

Example: Milwaukee

E

4

F

3

G

5

H

2

4

8

13

15

4

8

13

7

13

15

10

13

8

13

4

8

D

4

3

7

C

2

2

4

B

3

0

3

Start

0

0

0

A

2

2

0

4

2

8

4

2

0

4

1

0

0

The path formed by blue arrows is the critical path.

Example: Start from Step 3

Consider the following consulting project:

Identify the critical path in the project and determine the duration of the critical path and slack times for all activities.

Detailed solution is given in the document titled “In-class examples” posted under this week’s learning module.

Activity

Designation

Immed. Pred.

Time (Weeks)

Assess customer's needs

A

None

2

Write and submit proposal

B

A

1

Obtain approval

C

B

1

Develop service vision and goals

D

C

2

Train employees

E

C

5

Quality improvement pilot groups

F

D, E

5

Write assessment report

G

F

1

48

Variability in Activity Times

CPM assumes we know a fixed time estimate for each activity and there is no variability in activity times

PERT uses a probability distribution, Beta distribution, for activity times to allow for variability

Statistical analysis requires three reasonable estimates of activity times

Optimistic time (a)

Most likely time (m)

Pessimistic time (b)

Beta Distribution

The mean of the beta distribution can be estimated by

The variance of the beta distribution for each activity is

We use Beta Distribution to calculate the mean and variance of the completion time of each activity.

Example: Mean and Variance

Suppose that the project team has arrived at the following time estimates for activity B (site selection and survey) of the St. John’s Hospital project:

a = 7 weeks, m = 8 weeks, and b = 15 weeks

Calculate the expected time and variance for activity B.

Note that the expected time does not equal the most likely time. These will only be the same only when the most likely time is equidistant from the optimistic and pessimistic times.

51

Example: Solution

Expected completion time of the activity

Variance

= 1.78

Determine probabilities of project completion times

According to the Central Limit theorem, the expected completion of the whole project

, which is the mean of the normal distribution.

Assume that the activities times are independent, the variance of the completion time of the whole project

Determine probabilities of project completion times

Let D denote the expected project completion time, 6 weeks for example.

Using z-transformation,

z is the # of standard deviations to the left or right of zero in the standard normal distribution.

Using the z value, we then find the corresponding probability in Appendix I of the textbook. That probability is the probability of the project being completed in D amount of time.

Example: Determine Probability

Questions: What is the probability of completing the project in 35 weeks? Detailed solution is available in the doc “In-class Examples”.

Outline

Project Management

What is Project Management?

Three types of projects

Work Breakdown Structure (WBS)

Project Management Techniques: PERT and CPM

Cost-Time Trade-Offs and Project Crashing

A Critique of PERT and CPM

56

Project Crashing

Basic assumption: There is a relationship between activity completion time and project cost.

Time cost models: Determine the optimum point in time-cost tradeoffs

Activity direct costs: costs associated with expediting activities.

Project indirect costs: costs associated with sustaining the project.

Procedure for Project Crashing

Prepare a network diagram for the project

Determine the cost per unit of time to expedite each activity

Find out the critical path

Repeatedly shorten the critical path by crashing the least expensive activity based on the costs to crash per period.

Stop until it is not profitable to crash.

Finding the minimum cost schedule

Crash only activities that are critical.

Crash from least expensive to most expensive.

Each activity can be crashed until

it reaches it’s maximum time reduction

it causes another path to also become critical

it is more expensive to crash than not to crash

Continue until no more activities should be crashed.

59

Example: Cost to crash per period

Please calculate the cost to crash per period for each of the following activities.

Detailed solution available in the document “In-class examples”.

Example: Project crash

This project, under normal conditions takes 20 days. Suppose each day the project runs incurs an indirect project cost of $1400 (overhead). What activities should be crashed if any?

Detailed solution available in the document “In-class examples”.

Advantages of PERM/CRM

Especially useful when scheduling and controlling large projects

Straightforward concept and not mathematically complex

Graphical networks help highlight relationships among project activities

Critical path and slack time analyses help pinpoint activities that need to be closely watched

Project documentation and graphics point out who is responsible for various activities

Applicable to a wide variety of projects

Useful in monitoring not only schedules but costs as well

Disadvantages of PERM/CRM

Project activities have to be clearly defined, independent, and stable in their relationships

Precedence relationships must be specified and networked together

Time estimates tend to be subjective and are subject to fudging by managers

There is an inherent danger of too much emphasis being placed on the longest, or critical, path