Q1. Find the critical path and calculate the slack time for the following network

Q 2. A project has the following characteristics

Activity

Most optimistic time

(a)

Most pessimistic time (b)

Most likely time

(m)

(1 – 2)

(2 – 3)

(2 – 4)

(3 – 5)

(4 – 5)

(4 – 6)

(5 – 7)

(6 – 7)

(7 – 8)

(7 – 9)

(8 – 10)

(9 – 10)

1

1

1

3

2

3

4

6

2

5

1

3

5

3

5

5

4

7

6

8

6

8

3

7

1.5

2

3

4

3

5

5

7

4

6

2

5

Construct a PERT network. Find the critical path and variance for each event.