Consider the following project activities
Watch the following videos to help answer the question:
https://www.youtube.com/watch?v=WHkf4bE5MrE&list=PL1DBEEECCF25DD5B0
Consider the following project activities:
|
Activity |
Duration (Days) |
Predecessors |
|
A |
3 |
None |
|
B |
2 |
None |
|
C |
6 |
A |
|
D |
1.5 |
A,B |
|
E |
2.5 |
C,D |
|
F |
3.5 |
D |
|
G |
4 |
E,F |
Draw the project network diagram, identify all the paths through the network and their strengths, and identify all the critical activities and path(s). How long will the entire project take?