Consider the following project activities

profiletutor4helpyou
question.doc

Watch the following videos to help answer the question: 

https://www.youtube.com/watch?v=WHkf4bE5MrE&list=PL1DBEEECCF25DD5B0

Consider the following project activities:

Activity

Duration (Days)

Predecessors

A

3

None

B

2

None

C

6

A

D

1.5

A,B

E

2.5

C,D

F

3.5

D

G

4

E,F

Draw the project network diagram, identify all the paths through the network and their strengths, and identify all the critical activities and path(s). How long will the entire project take?