Two Assignments
Assignments/Assignment 1/Example for the charts and or graphs.pptx
Store Restructuring
Project Management Plan Overview
MAN 4583
April 26th, 2015
Project Integration plan
The Integration Management Plan will provide a consistent, cohesive process for initiating, planning, executing, controlling, and closing the project (NV H.I.E., 2012).
Project Integration Approach
Image: Exchange.nv.gov
Project Integration: overview
Integration Management
Scope Statement & Management
Time and Time Management
Costs & Cost Management
Quality & Quality Management
Communications Management
Human Resources Management
Procurement Management
Risk & Risk Management
Stakeholder Management
Scope Statement & Management
The scope of the project includes the planning, design, layout, installation and re-merchandising of five Tampa Bay stores
Project Objectives
Create a more user friendly shopping environment for customers
More efficient P.O.S. Terminals = Increased employee productivity
Improve & modernize layout & merchandise categorization of store
Boost company sales and profitability
Plan and Confirm Scope
Monitor and Control Scope
Close Scope Processes
Communications management
The Communications Management Plan defines the communication requirements for the Project, establishes the methods by which information will be distributed, and identifies the role of team’s members in the communication process (PMDocs)
Image: communicationplanstoday.blogspot.com
Risk & risk management
Risk Identification
Risk Assessment
Risk Response Development
Opportunity Management
Risk Response Control
Change Control Mgmt.
Contingency Planning
Contingency funding & Time Buffers
(Larson & Gray, p. 207-226, 2014)
Project risk will be managed using the following strategies which interact with each other to increase the likelihood and impact of positive events:
Time
* Store #1 is the biggest storefront of the owner’s franchise so this location will take slightly longer to restructure than the other stores since it is larger.
*Store #2 will also take slightly longer because the employees will still adjusting to what the best methods are for restructuring. This extra ½ of a week will also provide extra time to overcome any potential obstacles.
7
Project Start
March 23rd, 2015
Reconstruction on Store #1
Week 2
Store #1
Week 3
1st half of week Store#1
2nd half of week Store #2
Week 4
Week 5
Week 6
Project End
Store #2
Store #3
Store #4
Store #5
Last day of project: May 4th, 2015
Cost
Reconstruction Resource
Requirements and Budget
This illustration gives a breakdown of what resources the project requires and what every cost is in the project budget.
8
Staff labor
5 staff members * 35 hours per week * 7 weeks * $8.00/hour= $9,800
Signage
20 new signs * $20.00 per sign=
$400
Total Budget = $32,200
Terminals
11 terminals * $2,000 each= $32,200
Procurement Process
This diagram gives a step by step illustration of the procurement process from start to finish.
9
References
Larson, E. W., & Gray, C. F. (2014). Project Management, The Managerial Process (6th ed.). New York: McGraw Hill.
PMDocs. (n.d.). Sample Project Management Plan (PMP). Retrieved from Innovative Project Guide.com: http://innovativeprojectguide.com/sample-project-plans/14-sample-plans/161-sample-project-management-plan-pmp.html
PMI. (2013). Project Management Body of Knowledge (PMBOK Guide) (5th ed.). Newtown Square: Project Management Institute.
image2.gif
image3.png
image4.png
image5.png
Assignments/Assignment 1/Overview of topic.docx
Integration Management Plan
Integration Management Plan
The Hallmark Card & Gift Shop Store Restructuring Project is being undertaken as part of a plan to optimize the total customer shopping experience, thereby subsequently boosting sales. The project will result in the creation of a more efficient store layout that will increase the ease and speed with which customers are able to locate merchandise, while simultaneously improving team member productivity through the installation of new checkout terminals.
In order to ensure smooth execution of this venture, we recognize that an effective project integration approach must be employed. With this in mind, we have established an Integration Management Plan that will provide a consistent, cohesive process for initiating, planning, executing, controlling, and closing the project (NV H.I.E., 2012). Adoption of this plan further requires our commitment to the following objectives:
1. The adaptation, maintenance and execution of all project plans and processes during project startup (NV H.I.E., 2012)
2. The establishment, and clear communication and maintenance of the project’s overall organizational structure (NV H.I.E., 2012)
3. The involvement, where appropriate, of all relevant internal and external project stakeholders in the definition, maintenance, and execution of the project’s management processes (NV H.I.E., 2012)
4. The establishment and maintenance of the project’s technical and administrative environment (NV H.I.E., 2012)
5. The integration and coordination of all associated project plans and processes (NV H.I.E., 2012)
6. The execution of closure activities for all the project’s plans and processes during project shutdown (NV H.I.E., 2012)
Project Integration Approach
· Scope Definition and Management:
The project scope statement will define the precise parameters of the project, while the Scope Management Plan will explain the method and specific tasks that will be utilized during the process of executing and managing those parameters throughout the duration of the project. This area of focus also covers the change management process.
· Time and Time Management:
The project work schedule identifies the key tasks, activities, timelines, and resources that have been defined for the execution of this project. The Schedule Management Plan details the methodology for managing, executing and controlling the project schedule to ensure timely completion of the project (PMI, 2013).
· Costs and Cost Management:
The project estimates and budget describe the total anticipated project expenditure, while the Cost Management Plan explains the project team’s approach towards planning, financing, managing and controlling project costs to ensure that the project is completed within the agreed upon budget (PMI, 2013).
· Quality and Quality Management:
The quality segment focuses on a discussion of cost-benefit analysis, quality standards and deliverables and overall quality expectations (PMI, 2013). The Quality Management Plan identifies the project team’s methodology for ensuring that the project’s end result meets Hallmark store’s quality standards, and satisfies all other identified project goals.
· Communications Management:
The Communications Management Plan identifies the methods and processes that will be utilized to ensure the efficient creation, dissemination, retrieval, storage, management, controlling and monitoring of all project information (PMI, 2013).
· Human Resources Management:
The Human Resources Management Plan will discuss the project team members and their respective roles, as well as the overall approach towards organizing, managing, and leading the project team throughout the duration of the project.
· Procurement Management:
The Procurement Management Plan describes the chosen methodology for managing and controlling the purchasing or acquisition of all products and services required for project completion.
· Risk and Risk Management:
The Risk Assessment Form and Risk Breakdown Structure explain the identified project risks, while the Risk Response Matrix and the Risk Management Plan discuss the project team’s
approach towards planning, monitoring, controlling and mitigating risk throughout the duration of this project.
· Stakeholder Management:
The project’s stakeholders will be identified, and the Stakeholder Management Plan will further describe the processes that the team will engage in to communicate with and engage stakeholders in project decisions and activities (PMI, 2013).
Assignments/Assignment 1/Week 6 -Team Powerpoint Template.pptx
Store Restructuring
Project Management Plan Overview
MAN 4583
April 26th, 2015
image2.gif
Assignments/Assignment 1/YOUR INSTRUCTIONS (this is what needs to be done).docx
You are responsible for the following:
Each section requires 1 Page, including some charts if you can.
Please also refer to the Professor's Week 6 instructions and Rubric to be sure you have everything that is required....
1. Quality Management Plan —Format Needs Research, Pg.231> in PMBOK is vague but may be a start
2. Human Resources Management Plan (Format- Pg.264 PMBOK and attached document)
3. Stakeholder Management Plan (PMBOK Pg. 406) and information posted in the learning material for week six. (More research may be needed to find a format and charts)
As you create the three sections above, if you follow the Integration Management Plan that I emailed yesterday, it will serve as a guide and will also help to keep the overall project cohesive, as the Integration plan is really an overview of all the sections that follow.
In addition to the above, you are also responsible for creating overview/summary PowerPoint slides for each of these 3 sections. (No more than 1-2 slides per section, you should have the PowerPoint format in one of the last emails I sent...
(These slides will take the place of an Executive Summary)
Assignments/Assignment 2/Instructions.docx
Instructions
Consider agile programming in Information Technology and Agile Enterprises.
How can you apply event techniques: SCRUM (research this on the Internet), and Governance? Hint-use practical example.
Identify how these approaches can foster agility, promote innovation, and deliver the improvements that provide benefits to all stakeholders in an organization.
Apply your ideas to a general organization – NOT Information Technology.
Provide a Word document, use formal business writing (not APA), but do include a title page, double spacing, an introduction and a conclusion. Do cite all of your sources and provide references that comply with APA 6th ed.
Your net content should exceed 2 pages of quality writing. Diagrams and tables are welcome.