engineering with Excel
Assignment:
This exercise consists of a list of tasks for a home yard project. Working in Microsoft Project, you will create the task list, including summary tasks and their sub-tasks, create links between tasks and their predecessors. Set a start datefor your project of May 1st, 2015. Enter the following tasks, including the duration, where specified. Tasks with unspecified duration are summary tasks and the rest are sub-tasks. When completed save the file and submit the file via Canvas.
ID: Task List: Duration: Predecessors:
1 Preparation
2 Get trash bags 5 min
3 Pick up trash 20 min 2
4 Put gas in the equipment 5 min
5 Get the hedge clippers 5 min
6 Do the work
7 Trim weeds 30 min 3,4
8 Mow front yard 60 min 3,4
9 Edge sidewalk 20 min 3,4
10 Trim Hedge 30 min 5
11 Mow back yard 45 min 8
12 Clean up
13 Bag grass 35 min 7,9,10,11
14 Bundle trash 20 min 7,9,10,11
15 Haul trash 45 min 13,14
Saving/Naming Your File:
When you save your file make sure that your name and the project number are included in it.