CONstruction law - damages

profilemwade3
11.ppt

Chap 16
Proving costs and damages

  • How do you calculate damages??
  • Inability to prove with certainty may prevent full recovery
  • Need to determine true cost to evaluate the benefit of litigation

Basic premises on theory of damages

  • On breach of contract, the Court will generally attempt to put the claimant in the same position as if all parties performed the contract as intended
  • On a tort case, the Court will generally put the injured party in the same position as if the tort had not been committed
  • Tort damage is harder to define so Courts have limited to injury or damage and not economic loss so most suits are breach

Categories of damages

  • Direct or general damages – immediate impact of breach and are recoverable when proven
  • Consequential or special damages- indirect source of loss – to recover these must have been contemplated in contract and these are harder to prove
  • Punitive – awarded for fraud , bad conduct and negligence but rare in construction- intended to punish to prevent similar action in the future

Direct damages

  • Contractor

- idle labor and equip

- labor or mat’l escalations

- extended general conditions

  • Owner

- cost to correct work

- delay costs

Consequential damages

  • Contractor

- loss of another project and profits

- higher interest rates

  • Owner

- loss of use of building

- labor if employees cannot work

Recovery for consequential damages requires

  • Proof that the consequence was foreseeable in the normal course of events
  • Proof that the loss would not have occurred but for the breach
  • Proof that the amount of loss can be reasonably ascertained
  • Much higher burden of proof – except with express language

Issues related to recovery

  • Causation- prove the damages flow from the breach
  • Proper cost accounting records to document loss
  • Mitigation of damages- recovery is limited to the loss that was unavoidable
  • Betterment- cannot expect recovery for more than loss – can’t get “better” building than plans/specs

Methods of pricing claims

  • Total cost method
  • Segregated Cost Method
  • Modified total cost method
  • Quantum merit claims

Total cost method

  • Seeks to convert a fixed price contract to a fully reimbursed deal
  • Due to overly generous approach it is not frequently accepted by the Courts- does not account for any errors by the Contractor
  • All expenses are total and fee and overhead are added

Total cost method
Requirements

  • Other methods are impractical or impossible
  • Recorded costs are reasonable
  • Contractors bid must have been reasonable
  • Actions of the plaintiff-Contractor or sub – must not have caused any of the cost overrun

Segregated cost method

  • More difficult than total cost but more accurate and persuasive
  • All costs with the claim are segregated or separated- can be actual or estimation
  • Can be difficult to separate without detailed cost records
  • Good idea to separate costs as items come up- use cost codes

Modified total cost method

  • Combination of total and segregated
  • Modifies the calculation to show the cause and effect relationship with the costs and the cause of the claim
  • Must adjust the Contractor’s bid for any error to establish fair basis for claim
  • Focus on just the scope of work that impacts the claim
  • More favored by theCourts

Quantum merit

  • As much as deserved
  • Reasonable value approach
  • Measures damages under an implied contract based on theory that no one should unfairly benefit
  • Unjust enrichment- TV studio HVAC example
  • Often used when for subs with an owner where there is no contract

Contractor damages

  • Change in quality or quantity of the work
  • Changes in the method or sequence which includes delays, disruption and acceleration- floor changes example
  • Inefficiency is hard to prove actual costs- overtime, restricted access, trade stacking
  • Extended general conditions

Contractor damages

  • Breach before starting/ stopped job- lost profits, mobilization costs, estimating
  • Must be reasonable and use standard cost factors – unit prices, cost plus Fee/GC
  • Extra costs to track changes and home office support

Owner direct damages

  • Fail to start or fail to complete
  • Poor quality or defective work
  • Owner is due the difference between the contract and the cost to finish or correct
  • For substantially complete work use the cost and value rule –cost to complete or repair and value of actual work done
  • Fail to finish on time- delay costs- continue to rent in old location

Owner – consequential damages

  • Loss of use of the facility- profits
  • Cost of employees that are not productive
  • Increased interest rates or refinancing

Owner- liquidated damages

  • Agreed upon sum put in the contract
  • Established as actual damages cannot be determined
  • Must be reasonable estimation
  • Cannot be punitive
  • Courts will not uphold if Owner has a part in the delay or after substantial completion or final payment

Chap 17
Environmental and safety concerns

  • Many laws related environmental and safety issues
  • Have to have plan to address these in your projects
  • May involve permitting or licensing which is before you start work
  • Need to get the contract and insurance with correct language

Laws, Regulations , Agencies

  • Comprehensive Environmental Response, Compensation and Liability Act of 1990 CERCLA or “superfund” - mostly deals with clean –up
  • Resource Conservation Act of 1976 RCRA – deals with current handling
  • Clean Water Act
  • Clean Air Act
  • OSHA –Occupational Safety and Health Agency
  • EPA –Environmental Protection Agency

CERCLA -responsibilities

  • Current owner and operator
  • Owner and operator at the time the hazardous substance was dumped
  • Any party that arranged for the disposal of the hazardous substance owned by them or another party
  • Any person that accepted any hazardous substance for transport or disposal that results in a release

Superfund site liability

  • Very broad liability
  • One contractor held liable for just cut and fill on contaminated site even though they did not know and was years earlier
  • Any firm that sent waste there or if you bought a firm that did- Chicago hospital
  • Joint and several liability- liable as a whole not separable so if you contributed 20% then you are also liable for 100%

Other potential risks

  • Storm water run-off – applies to storm water run-off from constr. Sites > 1 acre- must get a permit and control run-off
  • File proper notices or penalties- $25k per day- civil and $25k per day plus 1 year in jail- criminal

Other potential risks

  • Air quality- dust from site or concrete dust from crushing for LEEDS
  • Asbestos- from demolition or hauling
  • Lead from paint
  • Mold exposure
  • PEL – Permissible exposure level- parts per million
  • Worker and public exposure risks

Asbestos abatement

Bag and tag

Asbestos abatement of floor tile-VAT- vinyl asbestos tile

Lead paint abatement

Minimizing risks

  • Prebid steps – review documents, site investigation, document asking the question or for reports
  • Test materials in question
  • AIA 201 has provision that addresses unanticipated hazardous substances that indemnify the contractor if no negligence
  • Stop work and notify the owner in writing
  • Obtain insurance or sub out if known

Toxic mold

  • Mold is common in nature and buildings but can be risky in some cases- confined spaces
  • No PEL so vague on exposure and damages
  • Some insurance has exclusions- “pollution exclusion” - check??

Mold loves drywall

Mold!!

Who is responsible for project safety?

  • The contractor and subs
  • Best to prevent accidents:

- reduces exposure to fines

-reduces premiums for workers comp and liability insurance

-reduces risk for accidents not covered by insurance

  • Send everyone home alive

Steps you can take

  • Safety manager
  • Written procedures
  • Training – before work and on the job
  • Work plans – before starting work
  • Preconstruction meetings
  • Risk assessments and mitigation plans before you start
  • Insurance
  • Emergency response plans
  • Legal reviews of contracts before you sign