Project schedule Changes

profilej_shina05
d4warehousemove_wbs_5.xls

Sheet1

Work Breakdown Structure
Project Name: District 4 Warehouse Move Note: All Forating is formulized. Only changing estimated durationn will change result and formatting automatically.
Project Manager:
Date: 1/8/11
1/3/11 Start date dd-mm-yy Starting date will chang finishin date automatically
Work Breakdown Structure Purpose and Limitations
The purpose of this worksheet is to: Identify the work to be done
Identify the types of resources required for the work
Develop estimates for each work element
This worksheet does not address: When the work will be completed
Use the following table to define the major deliverables and associated task detail for each deliverable. Use the example (in red) for help in determining how to break up the work and identify the Work ID numbers. Expand the table as needed.
Work Package Task Tasks Resource(s) Required Start Date Finish Date Estimated Duration (in days) Tasks Estimated Duration (in days) Work Package Starting date Mid Date Finish Date
ID 1/3/11 1/15/11 1/27/11
1 1 Project Kick-off 1/3/11 1/7/11 4 0.1666666667
2 1.1 Book location for meeting Project Manager 1/3/11 1/4/11 1 0.0666666667
3 1.2 Invite stakeholders Project Manager 1/3/11 1/4/11 1 0.0666666667
4 1.3 Prepare presentation Project Manager 1/3/11 1/4/11 1 0.0666666667
5 1.4 Conduct the meeting Project Manager and Attendees 1/3/11 1/4/11 1 0.0666666667
6 2 Project Documents 1/3/11 1/16/11 13 0.5416666667
7 2.1 Develop Charter/Scope Project Manager 1/3/11 1/5/11 2 0.1333333333
8 2.2 Develop WBS Project Manager and Workers 1/3/11 1/10/11 7 0.4666666667
9 2.3 Develop Project Plan Project Manager 1/3/11 1/5/11 2 0.1333333333
10 2.4 Develop Communication Plan Project Manager 1/3/11 1/5/11 2 0.1333333333
11 3 Status Reports/Meetings 1/3/11 1/6/11 3 0.125
12 3.1 Develop Status Report Project Manager 1/3/11 1/4/11 1 0.0666666667
13 3.2 Set schedule for team meetings Project Manager 1/3/11 1/4/11 1 0.0666666667
14 3.4 Set schedule for stakeholder meetings Project Manager 1/3/11 1/4/11 1 0.0666666667
15 4 Initial Planning Meetings with Vendors 1/3/11 1/8/11 5 0.2083333333
16 4.1 Meet with Framing/Drywall Project Manager and East Side Framing PM 1/3/11 1/4/11 1 0.0666666667
17 4.2 Meet with Electrical Project Manager and Sparks Electrical PM 1/3/11 1/4/11 1 0.0666666667
18 4.3 Meet with Plumbing Project Manager and Waterworks Plumbing PM 1/3/11 1/4/11 1 0.0666666667
19 4.4 Meet with Finish Work Project Manager and Woodcraft Carpentry PM 1/3/11 1/4/11 1 0.0666666667
20 4.5 Meet with Student Workers Project Manager and Student Workers Manger 1/3/11 1/4/11 1 0.0666666667
21 5 Electrical Permits 1/3/11 1/13/11 10 0.4166666667
22 5.1 Obtain Electrical Permits Sparks Electrical PM 1/3/11 1/13/11 10 0.6666666667
23 6 Plumbing Permits 1/3/11 1/13/11 10 0.4166666667
24 6.1 Obtain Plumbing Permits Waterworks Plumbing PM 1/3/11 1/13/11 10 0.6666666667
25 7 Building Permits 1/3/11 1/13/11 10 0.4166666667
26 7.1 Obtain Building Permits East Side Framing & Drywall PM 1/3/11 1/13/11 10 0.6666666667
27 8 Framing 1/3/11 1/27/11 24 1
28 8.1 Framing-Order Supplies East Side Framing & Drywall PM 1/3/11 1/6/11 3 0.2
29 8.2 Framing-Build East Side Framing & Drywall 1/3/11 1/18/11 15 1
30 8.3 Framing-Inspect City & County 1/3/11 1/8/11 5 0.3333333333
31 8.4 Framing-Project Sign-off Project Manager 1/3/11 1/4/11 1 0.0666666667
32 9 Electrical 1/3/11 1/22/11 19 0.7916666667
33 9.1 Electrical-Order Supplies Sparks Electrical PM 1/3/11 1/6/11 3 0.2
34 9.2 Electrical-Install Sparks Electrical 1/3/11 1/13/11 10 0.6666666667
35 9.3 Electrical-Inspect City & County 1/3/11 1/8/11 5 0.3333333333
36 9.4 Electrical-Project Sign-off Project Manager 1/3/11 1/4/11 1 0.0666666667
37 10 Plumbing 1/3/11 1/22/11 19 0.7916666667
38 10.1 Plumbing-Order Supplies Waterworks Plumbing PM 1/3/11 1/6/11 3 0.2
39 10.2 Plumbing-Install Waterworks Plumbing 1/3/11 1/13/11 10 0.6666666667
40 10.3 Plumbing-Inspect City & County 1/3/11 1/8/11 5 0.3333333333
41 10.4 Plumbing-Project Sign-off Project Manager 1/3/11 1/4/11 1 0.0666666667
42 11 Drywall 1/3/11 1/27/11 24 1
43 11.1 Drywall-Order Supplies East Side Framing & Drywall PM 1/3/11 1/6/11 3 0.2
44 11.2 Drywall-Install East Side Framing & Drywall 1/3/11 1/18/11 15 1
45 11.3 Drywall-Inspect City & County 1/3/11 1/8/11 5 0.3333333333
46 11.4 Drywall-Project Sign-off Project Manager 1/3/11 1/4/11 1 0.0666666667
47 12 Finish Work 1/3/11 1/27/11 24 1
48 12.1 Finish-Order Supplies Woodcraft Carpentry PM 1/3/11 1/6/11 3 0.2
49 12.2 Finish-Install Woodcraft Carpentry 1/3/11 1/18/11 15 1
50 12.3 Finish-Inspect City & County 1/3/11 1/8/11 5 0.3333333333
51 12.4 Finish-Project Sign-off Project Manager 1/3/11 1/4/11 1 0.0666666667
52 13 Workbenches 1/3/11 1/23/11 20 0.8333333333
53 13.1 Workbenches-Order Supplies Student Workers Manager 1/3/11 1/5/11 2 0.1333333333
54 13.2 Workbenches-Build Student Workers 1/3/11 1/18/11 15 1
55 13.3 Workbenches-Quality inspection Project Manager 1/3/11 1/5/11 2 0.1333333333
56 13.4 Workbenches-Project Sign-off Project Manager 1/3/11 1/4/11 1 0.0666666667
57 14 Equipment Packing 1/3/11 1/8/11 5 0.2083333333
58 14.1 Pack production equipment City Equipment Movers PM 1/3/11 1/5/11 2 0.1333333333
59 14.2 Pack non-production equipment City Equipment Movers 1/3/11 1/5/11 2 0.1333333333
60 14.3 Project Sign-off Project Manager 1/3/11 1/4/11 1 0.0666666667
61 15 Move 1/3/11 1/10/11 7 0.2916666667
62 15.1 Move production equipment Express Moving Company PM 1/3/11 1/6/11 3 0.2
63 15.2 Move non-production equipment Express Moving Company 1/3/11 1/6/11 3 0.2
64 15.3 Project Sign-off Project Manager 1/3/11 1/4/11 1 0.0666666667
65 16 Procurement Closure 1/3/11 1/8/11 5 0.2083333333
66 16.1 Review contract work Project Manager 1/3/11 1/6/11 3 0.2
67 16.2 Release contractors Project Manager 1/3/11 1/4/11 1 0.0666666667
68 16.3 Pay contractors Project Manager 1/3/11 1/4/11 1 0.0666666667
69 17 Project Closure 1/3/11 1/10/11 7 0.2916666667
70 17.1 Final report Project Manager 1/3/11 1/6/11 3 0.2
71 17.2 Archive documentation Project Manager 1/3/11 1/6/11 3 0.2
72 17.3 Lessons Learned Project Manager 1/3/11 1/4/11 1 0.0666666667
Task
Progress
Critical Path
Activities on critical path

Sheet2