Work Breakdown Structure
Project Name: District 4 Warehouse Move
Project Manager:
Date:
Work Breakdown Structure Purpose and Limitations
The purpose of this worksheet is to: Identify the work to be done
Identify the types of resources required for the work
Develop estimates for each work element
This worksheet does not address: When the work will be completed
Use the following table to define the major deliverables and associated task detail for each deliverable. Use the example (in red) for help in determining how to break up the work and identify the Work ID numbers. Expand the table as needed.
Work Package Task Tasks Resource(s) Required Estimated Duration (in days) Tasks Estimated Duration (in days) Work Package
ID
1 Project Kick-off 4
1.1 Book location for meeting Project Manager 1
1.2 Invite stakeholders Project Manager 1
1.3 Prepare presentation Project Manager 1
1.4 Conduct the meeting Project Manager and Attendees 1
2 Project Documents 13
2.1 Develop Charter/Scope Project Manager 2
2.2 Develop WBS Project Manager and Workers 7
2.3 Develop Project Plan Project Manager 2
2.4 Develop Communication Plan Project Manager 2
3 Status Reports/Meetings 3
3.1 Develop Status Report Project Manager 1
3.2 Set schedule for team meetings Project Manager 1
3.4 Set schedule for stakeholder meetings Project Manager 1
4 Initial Planning Meetings with Vendors 5
4.1 Meet with Framing/Drywall Project Manager and East Side Framing PM 1
4.2 Meet with Electrical Project Manager and Sparks Electrical PM 1
4.3 Meet with Plumbing Project Manager and Waterworks Plumbing PM 1
4.4 Meet with Finish Work Project Manager and Woodcraft Carpentry PM 1
4.5 Meet with Student Workers Project Manager and Student Workers Manger 1
5 Electrical Permits 10
5.1 Obtain Electrical Permits Sparks Electrical PM 10
6 Plumbing Permits 10
6.1 Obtain Plumbing Permits Waterworks Plumbing PM 10
7 Building Permits 10
7.1 Obtain Building Permits East Side Framing & Drywall PM 10
8 Framing 24
8.1 Framing-Order Supplies East Side Framing & Drywall PM 3
8.2 Framing-Build East Side Framing & Drywall 15
8.3 Framing-Inspect City & County 5
8.4 Framing-Project Sign-off Project Manager 1
9 Electrical 19
9.1 Electrical-Order Supplies Sparks Electrical PM 3
9.2 Electrical-Install Sparks Electrical 10
9.3 Electrical-Inspect City & County 5
9.4 Electrical-Project Sign-off Project Manager 1
10 Plumbing 19
10.1 Plumbing-Order Supplies Waterworks Plumbing PM 3
10.2 Plumbing-Install Waterworks Plumbing 10
10.3 Plumbing-Inspect City & County 5
10.4 Plumbing-Project Sign-off Project Manager 1
11 Drywall 24
11.1 Drywall-Order Supplies East Side Framing & Drywall PM 3
11.2 Drywall-Install East Side Framing & Drywall 15
11.3 Drywall-Inspect City & County 5
11.4 Drywall-Project Sign-off Project Manager 1
12 Finish Work 24
12.1 Finish-Order Supplies Woodcraft Carpentry PM 3
12.2 Finish-Install Woodcraft Carpentry 15
12.3 Finish-Inspect City & County 5
12.4 Finish-Project Sign-off Project Manager 1
13 Workbenches 20
13.1 Workbenches-Order Supplies Student Workers Manager 2
13.2 Workbenches-Build Student Workers 15
13.3 Workbenches-Quality inspection Project Manager 2
13.4 Workbenches-Project Sign-off Project Manager 1
14 Equipment Packing 5
14.1 Pack production equipment City Equipment Movers PM 2
14.2 Pack non-production equipment City Equipment Movers 2
14.3 Project Sign-off Project Manager 1
15 Move 7
15.1 Move production equipment Express Moving Company PM 3
15.2 Move non-production equipment Express Moving Company 3
15.3 Project Sign-off Project Manager 1
16 Procurement Closure 5
16.1 Review contract work Project Manager 3
16.2 Release contractors Project Manager 1
16.3 Pay contractors Project Manager 1
17 Project Closure 7
17.1 Final report Project Manager 3
17.2 Archive documentation Project Manager 3
17.3 Lessons Learned Project Manager 1

Sheet2

Task name Duration Start Date Finish Date Predecessor Resource Names
1.0 Project Kick-off 1day Mon 1/3/11 Mon 1/3/11
1.1 Book location for meeting 1day Mon 1/3/11 Mon 1/3/11 Project Manager
1.2 Invite Stakeholders 1day Mon 1/3/11 Mon 1/3/11 Project Manager
1.3 Prepare presentation 1day Mon 1/3/11 Mon 1/3/11 Project Manager
1.4 Conduct the meeting 1day Mon 1/3/11 Mon 1/3/11 Project Manager and A
2.0 Project Documents 7days Mon 1/3/11 Tue 1/11/11
2.1 Develop Charter/Scope 2days Mon 1/3/11 Tue 1/4/11 Project Manager
2.2 Develop WBS 7days Mon 1/3/11 Tue 1/4/11 Project Manager and W
2.3 Develop Project Plan 2days Mon 1/3/11 Tue 1/4/11 Project Manager
2.4 Develop Communication Plan 2days Mon 1/3/11 Tue 1/4/11 Project Manager
3.0 Status Reports/Meetings 1day Mon 1/3/11 Mon 1/3/11
3.1 Develop Status Report 1day Mon 1/3/11 Mon 1/3/11 Project Manager
3.2 Set schedule for team meetings 1day Mon 1/3/11 Mon 1/3/11 Project Manager
3.3 Set schedule for stakeholder meetings 1day Mon 1/3/11 Mon 1/3/11 Project Manager
4.0 Initial Planning Meetings with Vendors 1day Mon 1/3/11 Mon 1/3/11
4.1 Meet with Framing/Drywall 1day Mon 1/3/11 Mon 1/3/11 Project Manager and E
4.2 Meet with Electrical 1day Mon 1/3/11 Mon 1/3/11 Project Manager and S
4.3 Meet with Plumbing 1day Mon 1/3/11 Mon 1/3/11 Project Manager and W
4.4 Meet with Finish Work 1day Mon 1/3/11 Mon 1/3/11 Project Manager and W
4.5 Meet with Student Workers 1day Mon 1/3/11 Mon 1/3/11 Project Manager and S
5.0 Electrical Permits 15days Mon 1/3/11 Fri 1/19/11
5.1 Obtain Electrical Permits 15days Mon 1/3/11 Fri 1/19/11 Sparks Electrical PM
6.0 Plumbing Permits 15days Mon 1/3/11 Fri 1/19/11
6.1 Obtain Plumbing Permits 15days Mon 1/3/11 Fri 1/19/11 Waterworks Plumbing
7.0 Building Permits 15days Mon 1/3/11 Fri 1/19/11
7.1 Obtain Building Permits 15days Mon 1/3/11 Fri 1/19/11 East Side Framing & D
8.0 Framing 30days Mon 1/3/11 Fri 2/5/11
8.1 Framing-Order Supplies 6days Mon 1/3/11 Wed 1/8/11 East Side Framing & D
8.2 Framing-Build 30days Mon 1/3/11 Fri 2/5/11 East Side Framing & D
8.3 Framing-Inspect 20days Mon 1/3/11 Fri 1/24/11 City & County
8.4 Framing-Project Sign-off 2days Mon 1/3/11 Fri 1/4/11 Project Manager
9.0 Electrical 10days Mon 1/3/11 Fri 1/14/11
9.1 Electrical-Order Supplies 3days Mon 1/3/11 Wed 1/5/11 Sparks Electrical PM
9.2 Electrical-Install 10days Mon 1/3/11 Fri 1/14/11 Sparks Electrical
9.3 Electrical-Inspect 10days Mon 1/3/11 Fri 1/14/11 City & County
9.4 Electrical-Project Sign-off 1day Mon 1/3/11 Mon 1/3/11 Project Manager
10.0 Plumbing 10days Mon 1/3/11 Fri 1/14/11
10.1 Plumbing-Order Supplies 3days Mon 1/3/11 Wed 1/5/11 Waterworks Plumbing
10.2 Plumbing-Install 10days Mon 1/3/11 Fri 1/14/11 Waterworks Plumbing
10.3 Plumbing-Inspect 10days Mon 1/3/11 Fri 1/14/11 City & County
10.4 Plumbing-Project Sign-off 1day Mon 1/3/11 Mon 1/3/11 Project Manager
11.0 Drywall 30days Mon 1/3/11 Fri 2/5/11
11.1 Drywall-Order Supplies 6days Mon 1/3/11 Wed 1/8/11 East Side Framing & D
11.2 Drywall-Install 30days Mon 1/3/11 Fri 2/5/11 East Side Framing & D
11.3 Drywall-Inspect 20days Mon 1/3/11 Fri 1/24/11 City & County
11.4 Drywall-Project Sign-off 2days Mon 1/3/11 Fri 1/4/11 Project Manager
12.0 Finish Work 15days Mon 1/3/11 Fri 1/21/11
12.1 Finish-Order Supplies 3days Mon 1/3/11 Wed 1/5/11 Woodcraft Carpentry P
12.2 Finish-Install 15days Mon 1/3/11 Fri 1/21/11 Woodcraft Carpentry
12.3 Finish-Inspect 10days Mon 1/3/11 Fri 1/14/11 City & County
12.4 Finish-Project Sign-off 1day Mon 1/3/11 Mon 1/3/11 Project Manager
13.0 Workbenches 15days Mon 1/3/11 Fri 1/21/11
13.1 Workbenches-Order Supplies 2days Mon 1/3/11 Tue 1/4/11 Student Workers Mana
13.2 Workbenches-Build 15days Mon 1/3/11 Fri 1/21/11 Student Workers
13.3 Workbenches-Quality inspection 2days Mon 1/3/11 Tue 1/4/11 Project Manager
13.4 Workbenches-Project Sign-off 1day Mon 1/3/11 Mon 1/3/11 Project Manager
14.0 Equipment Packing 2days Mon 1/3/11 Tue 1/4/11
14.1 Pack production equipment 2days Mon 1/3/11 Tue 1/4/11 City Equipment Mover
14.2 Pack non-production equipment 2days Mon 1/3/11 Tue 1/4/11 City Equipment Mover
14.3 Project Sign-off 1day Mon 1/3/11 Mon 1/3/11 Project Manager
15.0 Move 3days Mon 1/3/11 Wed 1/5/11
15.1 Move production equipment 3days Mon 1/3/11 Wed 1/5/11 Express Moving Comp
15.2 Move non-production equipment 3days Mon 1/3/11 Wed 1/5/11 Express Moving Comp
15.3 Project Sign-off 1day Mon 1/3/11 Mon 1/3/11 Project Manager
16.0 Procurement Closure 3days Mon 1/3/11 Wed 1/5/11
16.1 Review contract work 3days Mon 1/3/11 Wed 1/5/11 Project Manager
16.2 Release contractors 1day Mon 1/3/11 Mon 1/3/11 Project Manager
16.3 Pay contractors 1day Mon 1/3/11 Mon 1/3/11 Project Manager
17.0 Project Closure 3days Mon 1/3/11 Wed 1/5/11
17.1 Final report 3days Mon 1/3/11 Wed 1/5/11 Project Manager
17.2 Archive documentation 3days Mon 1/3/11 Wed 1/5/11 Project Manager
17.3 Lessons Learned 1day Mon 1/3/11 Mon 1/3/11 Project Manager