Week 5
Project Planning – Developing the Project Plan and Determining Critical Path
Kimberley Manzo
MGT 402 A01
Laura Williams
Argosy University
ACTIVITIES/TASKS PRESENT IN THE CRITICAL PATH OF A MICROSOFT PROJECT PLAN (CRITICAL PATH)
1. Develop Charter/Scope
2. Develop communication plan
3. Meet with Electrical
4. Meet with Finish Work
5. Meet with Student Workers
6. Obtaining Building Permits
7. Framing Project Sign-off
8. Electrical
9. Electrical-Order Supplies
10. Plumbing
11. Plumbing Order Supplies
RISKS MOST LIKELY TO INCREASE PROJECT TIMELINE
1. Permits are not received as per the schedule-The stated task has a slack time i.e it cannot be delayed without affecting other activities of the project plan. It is also most likely to increase project timeline as it is bound by time constraints i.e as per the schedule.
2. Framing and drywall contractors are running behind schedule and can only produce half their crew as scheduled-This risk is also most likely to delay the project timeline as it is delayed while in the same case affecting the project timeline.