Unit VI Project
Activity Duration Predecessors
A 3 --
B 5 A
C 7 A
D 3 B, C
E 5 B
F 4 D
G 2 C
H 5 E, F, G
Activity Duration ES EF LS LF Slack
A 3 0 3 0 0 --
B 5 3 8 8 13 5
C 7 3 10 3 10 --
D 3 10 13 13 13 --
E 5 8 12 13 17 5
F 4 13 17 13 17
G 2 10 12 15 17 5
H 5 17 22 17 22 --