Unit VI Project
Part 1:
Put components for Part 1 of assignment here:
Develop an in-depth schedule for your initial project based on the Work Breakdown Structure you have
completed in Unit III. Please refer to the “INTEGRATED PROJECT: Developing the Project Schedule” in
Chapter 10, page 318 (Project Scheduling) for more information. (40pts total)
Be sure to include:
1. An activity precedence diagram (10pts)
2. An activity duration table (10pts)
3. A network diagram and Gannt charts (20pts)
Insert page break after Part 1
Part 2:
Put components for Part 2 of assignment here:
Please complete Case Study 10.2: Project Scheduling at Blanque Check Construction on pages 315-316
and answer the two questions at the end. (10pts)
Insert page break after Part 2
Part 3:
Put components for Part 3 here:
Develop the network activity chart and identify the critical path for a project based on the
information provided in the Gannt chart activity document. To access the Gannt chart activity document
refer to the hyperlink in the assignment directions. Draw the activity network as a Gantt chart. What is
the expected duration of the project? (25pts)
Activity Expected Duration Predecessor
A 5 days ----
B 10 days A
C 8 days A
D 1 day A
E 5 days B, C
F 10 days D, E
G 14 days F
H 3 days G
I 12 days F
j 6 days H, I
Insert page break after Part 3
Part 4:
Put components for Part 4 here:
Consider the project with the information provided in the Project Activity Network document. To
access the Project Activity document refer to the hyperlink in the assignment directions. Construct the
project activity network using AON methodology and label each node. Identify the critical path and other
paths through the network. (25pts)
Activity Duration Predecessors
A 3 --
B 5 A
C 7 A
D 3 B, C
E 5 B
F 4 D
G 2 C
H 5 E, F, G
Activity Duration ES EF LS LF Slack
A 3 0 3 0 0 --
B 5 3 8 8 13 5
C 7 3 10 3 10 --
D 3 10 13 13 13 --
E 5 8 12 13 17 5
F 4 13 17 13 17
G 2 10 12 15 17 5
H 5 17 22 17 22 --
Assignment should be submitted as one document to file upload.