Summary on excel work
Exercise 1 By Bader Aljuhani
| Capital Budgeting Exercise | |||||||
| 3 | 0 | 1 | 2 | 3 | 4 | 5 | |
| Cash Flows | -38,000 | -10,000 | 20,000 | 20,000 | 20,000 | 20,000 | 20,000 |
| DF @ 14% | 1 | 0.88 | 0.77 | 0.67 | 0.59 | 0.52 | 0.46 |
| Present value | -38000 | -8800 | 15400 | 13400 | 11800 | 10400 | 9200 |
| Total Present values of cash inflows | 51400 | ||||||
| 1.NPV | $13,400.00 | ||||||
| PI | -1.3526315789 | ||||||
| 2. IRR (approx) | 22.57% | ||||||
| MIRR SERVER: SERVER: Assuming that the reinvestment rate is 10%. | 17% | ||||||
| 3. The project should be accepted as it has positive NPV and a PI g |
Exercise 2 By Bader Aljuhani
| Mutually Exclusive Investments | |||
| Particulars | Project A | Project B | Ranking |
| Cash Outflow | -40000 | -90000 | |
| Cash Inflows | |||
| 1 | 16423 | 33466 | |
| 2 | 16423 | 33466 | |
| 3 | 16423 | 33466 | |
| 4 | 16423 | 33466 | |
| 5 | 16423 | 33466 | |
| Cumulative discount factor @ 10 % | 3.7907 | 3.7907 | |
| Total Present value of Cash Inflows | $62,254.67 | $126,859.57 | |
| 1. NPV | $22,254.67 | $36,859.57 | Project B |
| IRR | 30% | 25% | Project A |
| MIRR SERVER: SERVER: assuming a reinvestment rate of 8% | 19% | 17% | Project A |
| PI | -2 | -1 | Project A |
| 2 | |||
| Assuming No capital rationing, Project B must be selected as it has higher NPV | |||
| 3 | |||
| If these are independent projects, then decision can be based upon the one which has higher NPV and PI exceeds 1 |
Exercise 3 Abdullah Alhassun
| Replacement Decisions | |||
| Replacement to be done | Pv factor @ 8% | 3 year alternative | 4 year alternative |
| Cash outflow (T3/ T4) | 0.79/0.735 | -70000 | -70000 |
| PV factor @ 8% | 0.79 | 0.735 | |
| Present values | -55300 | -51450 | |
| Maintenance cost | |||
| Year 1 (T4) | 0.735 | -40000 | -50000 |
| Year 2 (T5) | 0.68 | -40000 | -50000 |
| Year 3 (T6) | 0.63 | -30000 | -35000 |
| Year 4 (T7) | 0.583 | -30000 | |
| Present values of maintenance cost | -75500 | -110290 | |
| NPV, If replacement done at T3 | ($130,800.00) | ||
| NPV, If replacement done at T4 | -161740 | ||
| Replacement to be done after every 3 years as it has lower negative NPV |
Exercise 4 Abdullah Alhassun
| 1 | Yes, this investment can be evaluated | |||
| The cash inflow for year 1 exceeds the initial investment and the project can be evaluated. It can also be dropped or shut down after year 1 which will substantiall saves a lot. | ||||
| 2 | ||||
| IRR | 10% | |||
| MIRR | 9% | |||
| Year | 0 | 1 | 2 | Total |
| Cash Flows | -100,000 | 230,900 | -133000 | |
| DF @ 5% | 0.95 | 0.91 | ||
| DF @15% | 0.87 | 0.76 | ||
| DF @ 18% | 0.85 | 0.72 | ||
| DF @ 25% | 0.80 | 0.64 | ||
| Present value @ 5% | 219816.80 | -121030.00 | 98786.80 | |
| Present value @ 15% | 200883.00 | -100548.00 | 100335.00 | |
| Present value @ 18% | 195572.30 | -95760.00 | 99812.30 | |
| Present value @ 25% | 0 | 184720 | -85120 | 99600.00 |
| Total Present values of cash inflows | 100,000 | |||
| 3. NPV @ 5% | 1,213.2 | Accepted | ||
| NPV @ 15% | -335.00 | Not accepted | ||
| NPV @ 18% | 187.70 | Accepted | ||
| NPV @ 25% | 400.00 | Accepted |
Exercise 5 Meshari Albishi
| Cost of New Machine | $400,000 | ||||||
| Operational Cost Saving | $150,000 | ||||||
| Life | 5 | ||||||
| Required Rate | 14% | ||||||
| Marginal Tax | 40% | ||||||
| Years | 0 | 1 | 2 | 3 | 4 | 5 | |
| Saving in Cost | ($400,000) | $150,000 | $150,000 | $150,000 | $150,000 | $150,000 | |
| Dep. | 80000 | 80000 | 80000 | 80000 | 80000 | ||
| EBIT | $70,000 | $70,000 | $70,000 | $70,000 | $70,000 | ||
| Tax | $28,000 | $28,000 | $28,000 | $28,000 | $28,000 | ||
| Net Profit | $42,000 | $42,000 | $42,000 | $42,000 | $42,000 | ||
| Cash Flow | $108,000 | $108,000 | $108,000 | $108,000 | $108,000 | ||
| PV | ($400,000) | $94,736.84 | $83,102.49 | $72,896.92 | $63,944.67 | $56,091.82 | |
| Cost of Old Machine | 100000 | ||||||
| Dep. Each year | 10000 | ||||||
| Total Five year Dep. | 50000 | ||||||
| Book Value of Machine | 50000 | ||||||
| market Value | 40000 | ||||||
| Loss on Sales of Old Machine | -10000 | ||||||
| Tax | -4000 | ||||||
| Total Loss | -6000 | ||||||
| A | NPV (Loss) | ($35,227.26) | |||||
| Years | Cash Flow | ||||||
| 0 | ($404,000) | ||||||
| 1 | $150,000 | ||||||
| 2 | $150,000 | ||||||
| 3 | $150,000 | ||||||
| 4 | $150,000 | ||||||
| 5 | $150,000 | ||||||
| IRR | 25% | ||||||
| MIRR | 18% | ||||||
| Project should not be accepted because NPV is negative. IRR is Positive but still company should consider the NPV. NPV refelects actuall gain and loss. | |||||||
| Assumptioon | 10% Reinvestment rate is assumed |
Exercise 6 Meshari Albishi
| Equipment Costing | $1,300,000 | ||||||
| Life (in years) | 5 | ||||||
| Tax | 30% | ||||||
| Required Rate | 15% | ||||||
| Years | 0 | 1 | 2 | 3 | 4 | 5 | |
| EBIT | $150,000 | $300,000 | $700,000 | $700,000 | $250,000 | ||
| Tax | $45,000 | $90,000 | $210,000 | $210,000 | $75,000 | ||
| Net Profit | $105,000 | $210,000 | $490,000 | $490,000 | $175,000 | ||
| Add: Dep | $365,000 | $470,000 | $750,000 | $750,000 | $435,000 | ||
| Cash Flow | ($1,300,000) | $470,000 | $680,000 | $1,240,000 | $1,240,000 | $610,000 | |
| Additional Working Capital | ($100,000) | ($200,000) | ($500,000) | ($500,000) | $400,000 | $900,000 | |
| Net Cash Flow | ($1,400,000) | $270,000 | $180,000 | $740,000 | $1,640,000 | $1,510,000 | |
| Present Value | ($1,400,000) | $234,782.61 | $136,105.86 | $486,562.01 | $937,675.32 | $750,736.87 | |
| NPV | $1,145,863 |