21 - Finish this in class or email to me by Midnight tomorrow night. 20 Pts

This is to be your work, no help from others. If you have trouble email me and I will give you hints and/or an extension of the time. -10

1) Draw the Network performing forward and backward passes giving ES,EF,LS, & LF in the box for each activity

2) Your staff has found a way to reduce the time to do activity H to 4 months. What will the effect be on the critical path and Project Duration if H is reduced to 4 mos?

3) Given crash costs in the last column which activity should be crashed for 1 month 1st?

Activity

Preceding

Activity

Duration months

Cost to Crash 1st Month

Start

0

D

Start

4

$1,000

A

Start

6

$1,200

F

D, A

7

$1,300

E

D

8

$1,400

G

F, E

5

$1,500

H

F

5

$1,600

B

G

7

$1,700

C

B

8

$1,800

End

C, H

0

Use this format for the activities boxes

Activity

ES

LS

Duration

EF

LF

1.

24 32

TASK C

8

25 33

17 24

TASKB

7

18 25

12 17

TASKG

5

13 18

4 12

TASKE

8

4 12

0 4

TASKD

4

0 4

33 33

END

0

33 33

0 0

Start

0 0

6 13

TASKF

7

6 13

28 33

TASKH

5

13 18

0 6

TASKA

6

0 6

The network diagram is wrong -5

Activity

ES

LS

Duration

EF

LF

2.

Crash D for 2 months Should crash activity on the critical path and lowest cost first -2

24 32

TASK C

8

25 33

$1800

17 24

TASKB

7

18 25

$1700

12 17

TASKG

5

13 18

$1500

4 12

TASKE

8

4 12

$1400

0 4

TASKD

4

0 4

$1000

33 33

END

0

33 33

0 0

Start

0 0

6 13

TASKF

7

6 13

$1300

28 33

TASKH

5

13 18

$1600

0 6

TASKA

6

0 6

$1200

Crashing D for 2 months = $ 2000

Crash END for 3 months

24 32

TASK C

8

25 33

$1800

17 24

TASKB

7

18 25

$1700

12 17

TASKG

5

13 18

$1500

4 12

TASKE

8

4 12

$1400

0 4

TASKD

4

0 4

$1000

33 33

END

0

33 33

0

0 0

Start

0 0

6 13

TASKF

7

6 13

$1300

28 33

TASKH

5

13 18

$1600

0 6

TASKA

6

0 6

$1200

Crashing END for 3 months = $0

Crash c for 1 month

24 32

TASK C

8

25 33

$1800

17 24

TASKB

7

18 25

$1700

12 17

TASKG

5

13 18

$1500

4 12

TASKE

8

4 12

$1400

0 4

TASKD

4

0 4

$1000

33 33

END

0

33 33

0 0

Start

0 0

6 13

TASKF

7

6 13

$1300

28 33

TASKH

5

13 18

$1600

0 6

TASKA

6

0 6

$1200

Crashing C for 1 month = $ 1800

Crash E for 2 months

24 32

TASK C

8

25 33

$1800

17 24

TASKB

7

18 25

$1700

12 17

TASKG

5

13 18

$1500

4 12

TASKE

8

4 12

$1400

0 4

TASKD

4

0 4

$1000

0,1,4,4 4,5,12,13 13,13,18,18 18,18,25,25 25,25,33,33

33 33

END

0

33 33

0 0

Start

0 0

6 13

TASKF

7

6 13

$1300

28 33

TASKH

5

13 18

$1600

0 6

TASKA

6

0 6

$1200

Crashing E for 2 months = $ 2800

Crash D for H 1 month

24 32

TASK C

8

25 33

$1800

17 24

TASKB

7

18 25

$1700

12 17

TASKG

5

13 18

$1500

4 12

TASKE

8

4 12

$1400

0 4

TASKD

4

0 4

$1000

33 33

END

0

33 33

0 0

Start

0 0

6 13

TASKF

7

6 13

$1300

28 33

TASKH

5

13 18

$1600

0 6

TASKA

6

0 6

$1200

Crashing D for 1months = $1600