3.10 The activities needed to build a prototype laser scanning

machine at Dave Fletcher Corp. are listed in the following

table. Construct an AON network for these activities.

ACTIVITY

IMMEDIATE

PREDECESSOR(S)

ACTIVITY

IMMEDIATE

PREDECESSOR(S)

A

E

B

B

F

B

C

A

G

C, E

D

A

H

D, F

PREDECESSOR(S) ACTIVITY

IMMEDIATE

􀁳 3.11 Dave Fletcher (see Problem 3.10 above) was able to determine

the activity times for constructing his laser scanning

machine. Fletcher would like to determine ES, EF, LS, LF, and

slack for each activity. The total project completion time and

the critical path should also be determined. Here are the activity

times:

ACTIVITY

TIME (WEEKS)

ACTIVITY

TIME (WEEKS)

A

6

E

4

B

7

F

6

C

3

G

10

D

2

H

7

3.17 Bill Fennema, president of Fennema Hospitality, has

developed the tasks, durations, and predecessor relationships in

the following table for building new motels. Draw the AON network

and answer the questions that follow.

TIME ESTIMATES (in weeks)

ACTIVITY

IMMEDIATE

PREDECESSOR(S)

OPTIMISTIC

MOST LIKELY

PESSIMISTIC

A

444

888

10

B

A

2

8

24

C

A

8

12

16

D

A

4

6

10

E

B

1

2

3

F

E,C

6

8

20

G

E,C

2

3

4

H

F

2

2

2

I

F

6

6

6

J

D,G,H

4

6

12

K

I,J

2

2

3

a) What is the expected (estimated) time for activity C?

b) What is the variance for activity C?

c) Based on the calculation of estimated times, what is the critical

path?

d) What is the estimated time of the critical path?

e) What is the activity variance along the critical path?

f) What is the probability of completion of the project before

week 36?