FINANCIAL MANAGEMENT #4
BCN 3753 FINANCIAL MANAGEMENT OF CONSTRUCTION ORGANIZATIONS
Spring 2015 - Homework Assignment #4 (50 Points)
Due Date: March 24, 2015 – 5:00 PM
(**Note: The information provided in each problem is sufficient to solve the problem
independent of your answers to the other problems)
Important Submission Instructions:
1. In class students should submit homework assignments in class (hard copy). The answers to all the questions should be turned in together (stapled) – Only students
who are absent are allowed to submit their homework on Blackboard
2. For submissions on Blackboard (FEEDS students), the answers to all the questions should be saved and submitted in a SINGLE PDF file. Otherwise, the HW will not be
graded.
3. For this assignment, you are NOT ALLOWED to use Excel Spreadsheet for solving the problems.
1. Given cash flows for an investment of $5,800 at time 0, determine the IRR to the nearest
second decimal place. (25 points)
(Hint: Try 10% and 12% and Interpolate)
Year 0 1 2 3 4
Cash Flow -$5,800 $1,800 $1,800 $1,800 $2,000
2. Two hazardous environment facilities are being evaluated, with the projected life of each facility being 10 years. The cash flows are as follows:
Alternative A Alternative B
First cost $615,000 $300,000
Maintenance and operating cost $10,000 $25,000
Annual benefits $158,000 $92,000
Salvage value $65,000 -$5,000
The company uses a MARR of 15%. Using rate of return analysis, which alternative should be