Operations CASE, SLP and TD
© 2006 Prentice Hall, Inc.
3 – *
Strategic Importance of
Project Management
Bechtel Kuwait Project:
8,000 workers
1,000 construction professionals
100 medical personnel
2 helicopter evacuation teams
6 full-service dining halls
27,000 meals per day
40 bed field hospital
*
© 2006 Prentice Hall, Inc.
3 – *
Strategic Importance of
Project Management
Microsoft Windows Longhorn Project:
hundreds of programmers
millions of lines of code
millions of dollars cost
Ford Redesign of Mustang Project:
450 member project team
Cost $700-million
25% faster and 30% cheaper than comparable project at Ford
*
© 2006 Prentice Hall, Inc.
3 – *
Single unit
Many related activities
Difficult production planning and inventory control
General purpose equipment
High labor skills
Project Characteristics
*
© 2006 Prentice Hall, Inc.
3 – *
Examples of Projects
- Building Construction
- Research Project
*
© 2006 Prentice Hall, Inc.
3 – *
Project Organization
Works Best When
Work can be defined with a specific goal and deadline
The job is unique or somewhat unfamiliar to the existing organization
The work contains complex interrelated tasks requiring specialized skills
The project is temporary but critical to the organization
*
© 2006 Prentice Hall, Inc.
3 – *
Management of Projects
Planning - goal setting, defining the project, team organization
Scheduling - relates people, money, and supplies to specific activities and activities to each other
Controlling - monitors resources, costs, quality, and budgets; revises plans and shifts resources to meet time and cost demands
*
© 2006 Prentice Hall, Inc.
3 – *
- Planning
- Objectives
- Resources
- Work break-down schedule
- Organization
- Scheduling
- Project activities
- Start & end times
- Network
- Controlling
- Monitor, compare, revise, action
Project Management Activities
*
© 2006 Prentice Hall, Inc.
3 – *
Project Planning, Scheduling, and Controlling
Figure 3.1
Before Start of project During
project Timeline project
*
© 2006 Prentice Hall, Inc.
3 – *
Project Planning, Scheduling, and Controlling
Figure 3.1
Before Start of project During
project Timeline project
*
© 2006 Prentice Hall, Inc.
3 – *
Project Planning, Scheduling, and Controlling
Figure 3.1
Before Start of project During
project Timeline project
*
© 2006 Prentice Hall, Inc.
3 – *
Project Planning, Scheduling, and Controlling
Figure 3.1
Before Start of project During
project Timeline project
*
© 2006 Prentice Hall, Inc.
3 – *
Project Planning, Scheduling, and Controlling
Figure 3.1
Before Start of project During
project Timeline project
Budgets
Delayed activities report
Slack activities report
Time/cost estimates
Budgets
Engineering diagrams
Cash flow charts
Material availability details
CPM/PERT
Gantt charts
Milestone charts
Cash flow schedules
*
© 2006 Prentice Hall, Inc.
3 – *
Establishing objectives
Defining project
Creating work breakdown structure
Determining
resources
Forming organization
Project Planning
*
© 2006 Prentice Hall, Inc.
3 – *
Often temporary structure
Uses specialists from entire company
Headed by project manager
Coordinates activities
Monitors schedule
and costs
Permanent
structure called
‘matrix organization’
Project Organization
*
© 2006 Prentice Hall, Inc.
3 – *
A Sample Project Organization
Figure 3.2
Test
Engineer
Mechanical
Engineer
Project 1
Project
Manager
Technician
Technician
Project 2
Project
Manager
Electrical
Engineer
Computer
Engineer
Marketing
Finance
Human
Resources
Design
Quality
Mgt
Production
President
*
© 2006 Prentice Hall, Inc.
3 – *
Matrix Organization
Marketing Operations Engineering Finance
Project 1
Project 2
Project 3
Project 4
*
© 2006 Prentice Hall, Inc.
3 – *
The Role of
the Project Manager
Highly visible
Responsible for making sure that:
- All necessary activities are finished in order and on time
- The project comes in within budget
- The project meets quality goals
- The people assigned to the project receive motivation, direction, and information
*
© 2006 Prentice Hall, Inc.
3 – *
The Role of
the Project Manager
Highly visible
Responsible for making sure that:
- All necessary activities are finished in order and on time
- The project comes in within budget
- The project meets quality goals
- The people assigned to the project receive motivation, direction, and information
Project managers should be:
Good coaches
Good communicators
Able to organize activities from a variety of disciplines
*
© 2006 Prentice Hall, Inc.
3 – *
Ethical Issues
- Bid rigging – divulging confidential information to give some bidders an unfair advantage
- “Low balling” contractors – try to “buy” the project by bidding low and hope to renegotiate or cut corners
- Bribery – particularly on international projects
- Expense account padding
- Use of substandard materials
- Compromising health and safety standards
- Withholding needed information
- Failure to admit project failure at close
*
© 2006 Prentice Hall, Inc.
3 – *
Work Breakdown Structure
Level
- Project
- Major tasks in the project
- Subtasks in the major tasks
- Activities (or work packages)
to be completed
*
© 2006 Prentice Hall, Inc.
3 – *
Work Breakdown Structure
Figure 3.3
Level ID
Level Number Activity
1 1.0 Develop/launch Windows Longhorn OS
2 1.1 Development of GUIs
2 1.2 Ensure compatibility with earlier
Windows versions
3 1.21 Compatibility with Windows ME
3 1.22 Compatibility with Windows XP
3 1.23 Compatibility with Windows 2000
4 1.231 Ability to import files
*
© 2006 Prentice Hall, Inc.
3 – *
Identifying precedence relationships
Sequencing activities
Determining activity times & costs
Estimating material and worker requirements
Determining critical activities
Project Scheduling
*
© 2006 Prentice Hall, Inc.
3 – *
Purposes of Project Scheduling
Shows the relationship of each activity to others and to the whole project
Identifies the precedence relationships among activities
Encourages the setting of realistic time and cost estimates for each activity
Helps make better use of people, money, and material resources by identifying critical bottlenecks in the project
*