Can anyone show me how to create a risk managment sheet ?
Assignment: The Stevens Company is converting from the SQL Server database to the Oracle® database.
Using the sample shown below, create a Risk Information Sheet for at least five risks that might be encountered during the conversion.
|
Risk Information Sheet |
|
Risk id: PO2-4-32 |
|
Date: March 4, 2014 |
|
Probability: 80% |
|
Impact: High |
|
Description: |
|
Over 70% of the software components scheduled for reuse will be integrated into the application. The remaining functionality will have to be custom developed. |
|
Refinement/Context: |
|
· Certain reusable components were developed by a third party with no knowledge of internal design standards. · Certain reusable components have been implemented in a language that is not supported on the target environment. |
|
|
|
Mitigation/Monitoring: |
|
· Contact third party to determine conformance to design standards. · Check to see if language support can be acquired. |
|
|
|
Management/Contingency Plan/Trigger: |
|
· Develop a revised schedule assuming that 18 additional components will have to be built. · Trigger: Mitigation steps unproductive as of March 30, 2014 |
|
|
|
Current Status: |
|
In process |
|
Originator: |
|
Jane Manager |