Unit VII Assessment
Copyright 2012 John Wiley & Sons, Inc.
Chapter 10
Monitoring and Information Systems
10-*
Terms
- Monitoring - Collecting, recording, and reporting information concerning any and all aspects of project performance
- Controlling - Uses the data supplied by monitoring to bring actual performance into compliance with the plan
- Evaluation - Judgments regarding the quality and effectiveness of project performance
10-*
The Planning–Monitoring–Controlling Cycle
- We mainly want to monitor:
Time (schedule)
Cost (budget)
Scope (project performance)
- Closed-loop system
Revised plans and schedules following corrective actions
10-*
Project Authorization and Expenditure Control System Information Flow
Figure 10-1
10-*
Designing the Monitoring System
- Identify key factors to be controlled
Scope
Cost
Time
- Information to be collected must be identified
10-*
Designing the Monitoring System Continued
- Do not want to avoid collecting necessary data because it is hard to get
- Do not want to collect too much data
- The next step is to design a reporting system that gets the data to the proper people in a timely and understandable manner
10-*
Data Collection
- Once we know the data we want, we need to decide how to collect it
- Should the data be collected after some event?
- Should it be collected on a regular basis?
- Are there any special forms needed for data collection?
10-*
Much Data Involves
- Frequency counts
- Raw numbers
- Subjective numeric ratings
- Indicators
- Verbal measures
10-*
Information Needs and Reporting
- Everyone should be tied into the reporting system
- Reports should address each level
- Not at same depth and frequency for every level
Lower-level needs detailed information
Senior management levels need overview reports
- Report frequency is typically high at low levels and less frequent at higher levels
Everyone concerned with the project should be appropriately tied into the project reporting system. The monitoring system ought to be constructed so that it addresses every level of management, but reports need not be of the same depth or at the same frequency for each level. Lower-level personnel have a need for detailed information about individual tasks and the factors affecting such tasks. Report frequency is usually high. For the senior management levels, overview reports describe progress in more aggregated terms with less individual task detail unless senior management has a special interest in a specific activity or task. Reports are issued less often. In both cases, the structure of the reports should reflect the work breakdown structure, with each managerial level receiving reports that allow the exercise of control at the relevant level.
10-*
The Reporting Process
- Reports must contain relevant data
- Must be issued frequently
- Should be available in time for control
- Distribution of project reports depends on interest
For senior management, may be few milestones
For project manager, there may be many critical points
The relationship of project reports to the project action plan or work breakdown structure is the key to the determination of both report content and frequency. Reports must contain data applicable to the control of specific tasks that are being carried out according to a specific schedule. The frequency of reporting should be great enough to allow control to be exerted during or before the period in which the task is scheduled for completion. In addition to the criterion that reports should be available in time to be used for project control, the timing of reports should generally correspond to the timing of project milestones.
The distribution of project reports depends on who is interested. For senior management, there may be only a few milestones, even in large projects. For the project manager there may be many critical points in the project schedule at which major decisions must be made, large changes in the resource base must be initiated, or key technical results achieved. Similar points relevant to lower levels relate to finer detail and occur with higher frequency.
10-*
Benefits of Detailed and Timely Reports
- Mutual understanding of the goals
- Awareness of the progress of parallel activities
- Understanding the relationship of tasks
- Early warning signals of problems
- Minimizing the confusion
- Higher visibility to top management
- Keeping client up to date
10-*
Report Types
- Routine - Reports that are issued on a regular basis or each time the project reaches a milestone
- Exception - Reports that are generated when an usual condition occurs or as an informational vehicle when an unusual decision is made
- Special Analysis - Reports that result from studies commissioned to look into unexpected problems
10-*
Meetings
- Reports do not have to be written
- They can be delivered verbally in meetings
- Projects have too many meetings
- The trick is to keep them to as few as possible
10-*
Meeting Rules
- Use meetings to make group decisions
- Start and end on time and have an agenda
- Do your homework before the meeting
- Take minutes
- Avoid attributing remarks to individuals in minutes
- Avoid overly formal rules of procedure
- Call meeting for serious problems
10-*
Common Reporting Problems
- Too much detail
- Poor interface between the data/procedures of the project and the information system of the parent company
- Poor correspondence between the planning process and the monitoring process
10-*
Earned Value Analysis
- Have covered monitoring parts
Timing and coordination between individual tasks is important
- Must also monitor performance of entire project
Crux of matter should not be overlooked
- One way is by using an aggregate performance measure called earned value
10-*
The Earned Value Chart and Calculations
- Actual against baseline ignores the amount of work accomplished
- Earned value incorporates work accomplished
- Multiply the estimated percent work complete for each task by the planned cost
- Only need percent complete estimate for tasks currently in progress
10-*
Rules to Aid in Estimating Percent Completion
- 50-50 rule
- 0-100 percent rule
- Critical input use rule
- Proportionality rule
10-*
The Earned Value Chart
Figure 10-6
10-*
Variances
- Variances can help analyze a project
A negative variance is bad
Cost and schedule variances are calculated as the earned value minus some other measure
- Will look at some of the more common ones
10-*
Cost Variance (CV)
- CV = EV – AC
- Negative variance indicates a cost overrun
- Magnitude depends on the costs
10-*
Schedule Variance (SV)
- SV = EV – PV
- Negative variance indicates you are behind schedule
- Measured using costs
10-*
Time Variance (TV)
- TV = ST – AT
- Negative variance indicates you are behind schedule
10-*
Indices
- Cost Performance Index
CPI = EV/AC
- Schedule Performance Index
SPI = EV/PV
- Time Performance Index
TPI = ST/AT
- Cost Schedule Index
CSI = EV2/(AC)(PV)
10-*
“To complete” and “At Completion”
- Project manager reviewing what is complete and what remains
- Final cost and final completion date are moving targets
- The project manager compiles these into a to complete forecast
- Actual + forecast = final date and cost at completion
10-*
ETC and EAC
ETC = (BAC + EV)/CPI
EAC = ETC + AC
where,
ETC = Estimated cost to complete
BAC = Budget at completion
EV = Earned value
CPI = Cost performance index
EAC = Estimated cost at completion
AC = Amount expended to date (actual cost)
10-*
Milestone Reporting
- Reports that are created when a project reaches a major milestone
- They are designed to keep everyone up-to-date on project status
- For executives and clients, these may be the only reports they receive
10-*
Computerized PMIS (Project Management Information Systems)
- Real projects are often large
Hundreds of tasks
Thousands of work units
- Reporting is clearly a job for the computer
- Project management information systems were one of the earlier applications
- Initially focus was on scheduling
- Now it includes, earned values, variances, and more
10-*
PMIS Errors
- Managing the PMIS
- Computer paralysis
- PMIS verification
- Information overload
- Project isolation
- Computer dependence
- PMIS misdirection
10-*
PMIS Desirable Attributes
- Friendliness
- Schedules
- Calendars
- Budgets
- Reports
- Graphics
- Charts
- Migration
- Consolidation
- Access