A. Predecessors and Successors I
Please write all your response in a single MS Word document covering all questions and exercises, and paste (do not attach) the screen shots into the document in-line with your text.� It makes it much easier to read� -- and grade.� Please include screen shots of each step, not just one screen shot before or one after.
Note:� These are not trick questions, though (as with many of the MS Project exercises) you need to read them carefully.� Some people seem to misread the question and do the wrong thing.
A.1. You've seen in Appendix A how to enter the predecessors for a task.� What is one method to enter successors (that's right, successors, not predecessors) for an MS project task?� (Note:� This is not asking how to display the Successors column; that's the next question.� This asks how to enter successors for a task.)� Describe AND provide a screen shot of the steps.
A.2. What is one method to show the successors field (column)?� Describe AND provide a screen shot of the steps.
A.3. What is one method to enter the project start date?� Not the start date of a task (that's a different question, below) -- not even of the first task -- but the start date of the entire project.� Describe AND provide a screen shot of the steps.
A.4. What version of MS Project did you use for this?