See Description
Work breakdown structure
WBS
Columbia Southern University
Tiffany Williams
The work breakdown structure is a key project deliverable that organizes the team's work into
manageable sections. Is a "deliverable oriented hierarchical decomposition of the work to be executed
by the project team." The work breakdown structure visually defines the scope into manageable chunks
that a project team can understand, as each level of the work breakdown structure provides further
definition and detail. (Work Breakdown Structure (WBS). (n.d.). Retrieved from
https://www.workbreakdownstructure.com)IN this case, I would use a three level work breakdown to
illustrate the processes in the construction project. In the paper am going to outline the work break
down structure for the construction project of a warehouse showing the various stages, participants, the
budget, as well as project timeline and constraints.
The depiction of the WBS will be using both charts and tables indicating codes for the various activities.
The idea process can be illustrated in the diagram below together with the OBS
WBS #: 1.1.1 Task: Create Plan
Est. Level of
Effort:
40 hrs Owner: Project Manager
Resources Needed: Subject Matter Experts Work
Products:
MS Project Plan
Description of
Task:
Development of a detailed project plan that lists all key resources,
tasks, milestones, dependencies, and durations.
Input: 1. Approved Project Charter 2. SMEs
Dependencies: 3. Approval of Budget
Risk: 4. Changes to IT Apps plans and deliverables 5. IT Apps implementation releases, which conflict with
implementation
WBS #: 1.1.2 Work Item: Make Budget
Est. Level of
Effort:
16 hrs. Owner: Project Manager
Resources Needed: CFO, CIO, Executive
Sponsor
Work
Products:
ITPR
Description of
Task:
Development and documentation of the project budget based on
plan and resources.
Input: 6. Approved Project Charter 7. SMEs
Dependencies: 8. Approval of Project Charter
Risk: 9. Collapse of house
WBS FIELDS
WBS
# Task Description of Task
Work
Products Owners
Est. Level
of Effort
1 PLANNIN
G
All task management and
management activities
1.1 Plan and
Supervise
Roll-up Task Project
Manager
N/A
1.1.
1
Create Plan Development of WBS, work
package identification,
schedule formulation,
staffing projection, resource
estimation. Followed by
development of a detail
project plan that list all the
key resources, task,
milestones, dependencies,
and duration.
WBS,
WBS
Dictionary,
MS Project
Plan
Project
Manager
40 hrs
1.1.
2
Create
Budget
Development and
documentation of the project
budget based on plan and
resources
ITPR Project
Manager
40 hrs
1.1.
3
Prepare
Disburseme
nt /
Reconciliati
on
Development of
disbursement process for the
project including
acceptance/approval forms.
Purchase
Orders,
Deliverable
Product
Acceptance
Form
CFO 40 hrs
1.1.
4
Coordinate
Activities
Ongoing planning activities
for the project including
weekly meetings
Meeting
Minutes
Project
Manager
8 hrs/week
Tabular View
The Tabular View is a nicely organized table view of the WBS. It is a good option
for organizations which prefer table formats.
Level 1 Level 2 Level 3
1 Widget Management
System
1.1 Initiation 1.1.1 Evaluation & Recommendations
1.1.2 Develop Project Charter
1.1.3 Deliverable: Submit Project
Charter
1.1.4 Project Sponsor Reviews Project
Charter
1.1.5 Project Charter Signed/Approved
1.2 Planning 1.2.1 Create Preliminary Scope
Statement
1.2.2 Determine Project Team
1.2.3 Project Team Kickoff Meeting
1.2.4 Develop Project Plan
1.2.5 Submit Project Plan
1.2.6 Milestone: Project Plan Approval
1.3
Execution
1.3.1 Project Kickoff Meeting
1.3.2 Verify & Validate Requirements
1.3.3 Design map layout of warehouse
1.3.4 Procure materials for construction
1.3.9 Commence construction
1.4 Control 1.4.1 Project Management
1.4.2 Project Status Meetings
1.4.3 Risk Management
1.4.4 Update Project Management Plan
1.5 Closeout 1.5.1 Audit Procurement
1.5.2 Document Lessons Learned
1.5.3 Update Files/Records
1.5.4 Gain Formal Acceptance
1.5.5 Archive Files/Documents
In tabular form the WBS for the project is represented below with codes
Level WBS Code Element Name
1 1 Widget Management System
2 1.1 Initiation
3 1.1.1 Evaluation & Recommendations
3 1.1.2 Develop Project Charter
3 1.1.3 Deliverable: Submit Project Charter
3 1.1.4 Project Sponsor Reviews Project Charter
3 1.1.5 Project Charter Signed/Approved
2 1.2 Planning
3 1.2.1 Create Preliminary Scope Statement
3 1.2.2 Determine Project Team
3 1.2.3 Project Team Kickoff Meeting
3 1.2.4 Develop Project Plan
3 1.2.5 Submit Project Plan
3 1.2.6 Milestone: Project Plan Approval
2 1.3 Execution
3 1.3.1 Project Kickoff Meeting
3 1.3.2 Verify & validation
3 1.3.3 Design map of the warehouse
3 1.3.4 Procure construction materials
3 1.3.5 Commence construction
3 1.3.6 Monitor progress
3 1.3.7 Access if project completion meets standards
3 1.3.8 Orientation of employees
3 1.3.9 Execute operation
2 1.4 Control
3 1.4.1 Project Management
3 1.4.2 Project Status Meetings
3 1.4.3 Risk Management
3 1.4.4 Update Project Management Plan
2 1.5 Closeout
3 1.5.1 Audit Procurement
3 1.5.2 Document Lessons Learned
3 1.5.3 Update Files/Records
3 1.5.4 Gain Formal Acceptance
3 1.5.5 Archive Files/Documents
The chart below illustrates the steps in the actual construction process
An easy way to think about the work breakdown structure is like an outline or map of our project. A
work breakdown structure starts with the project as the top level deliverable and is further decomposed
into sub-deliverables using the outline hierarchy as above
The undertaking group makes the work breakdown structure by recognizing the major practical
deliverables and subdividing those deliverables into littler frameworks and sub-deliverables. These sub-
deliverables are further decayed until a solitary individual can be relegated. At this level, the particular
work bundles needed to create a sub- deliverable are distinguished and assembled together. The work
bundle speaks to the rundown of undertakings or "to-dos" to create the particular unit of work. In the
event that you've seen point by point undertaking calendars, then you'll perceive the assignments under
the work bundle as the "stuff" individuals need to finish by a particular time and inside a particular level
of exertion.
From an expense viewpoint, these work bundles are gathered and doled out to a particular division to
deliver the work. These offices or expense records are characterized in a hierarchical breakdown
structure and are allotted a financial plan to deliver the particular deliverables. By coordinating the
expense accounts from the hierarchical breakdown structure and the venture's work breakdown
structure, the whole association can track budgetary advancement notwithstanding extend execution.
Finally the project timeline and completion dates are as shown below
Activities Dependencies Resources Activity
duration
days
Start date Due date
Project start
date
A Initiation Project
officer
7 1 st Dec
2014
7 th
Dec
2015
B Planning Project
office
7 8 th
Dec
2014
14 th Dec
2015
C Execution B IT 4 15 th Dec 18
th Jan
2-15
2014
D Monitoring
and control
A,B.C IT 7 19 th Jan
2015
25 th Jan
2015
E Closing A,B,C,D Project team 6 26 th Jan
2015
31 st Jan
2015