A-Plus Writer

profileepoe04
project_plan_check_-_district4move_1.doc

ID WBS Task Name Duration Start Finish Predecessors Resource Names January Februar

2/1 2/2 1/2 1/9 1/16 1/23 1/30 2/6

1 1 Project Kick-off 1 day Mon 1/3/11 Mon 1/3/11

2 1.1 Book location for meeting 1 day Mon 1/3/11 Mon 1/3/11 Project Manager Project Manager

3 1.2 Invite stakeholders 1 day Mon 1/3/11 Mon 1/3/11 Project Manager Project Manager

4 1.3 Prepare presentation 1 day Mon 1/3/11 Mon 1/3/11 Project Manager Project Manager

5 1.4 Conduct the meeting 1 day Mon 1/3/11 Mon 1/3/11 Project Manager and A Project Manager and Attend

6 2 Project Documents 7 days Mon 1/3/11 Tue 1/11/11

7 2.1 Develop Charter/Scope 2 days Mon 1/3/11 Tue 1/4/11 Project Manager Project Manager

8 2.2 Develop WBS 7 days Mon 1/3/11 Tue 1/11/11 Project Manager and W Project Manager and

9 2.3 Develop Project Plan 2 days Mon 1/3/11 Tue 1/4/11 Project Manager Project Manager

10 2.4 Develop Communication Plan 2 days Mon 1/3/11 Tue 1/4/11 Project Manager Project Manager

11 3 Status Reports/Meetings 1 day Mon 1/3/11 Mon 1/3/11

12 3.1 Develop Status Report 1 day Mon 1/3/11 Mon 1/3/11 Project Manager Project Manager

13 3.2 Set schedule for team meetings 1 day Mon 1/3/11 Mon 1/3/11 Project Manager Project Manager

14 3.3 Set schedule for stakeholder meetings 1 day Mon 1/3/11 Mon 1/3/11 Project Manager Project Manager

15 4 Initial Planning Meetings with Vendors 1 day Mon 1/3/11 Mon 1/3/11

16 4.1 Meet with Framing/Drywall 1 day Mon 1/3/11 Mon 1/3/11 Project Manager and E Project Manager and East S

17 4.2 Meet with Electrical 1 day Mon 1/3/11 Mon 1/3/11 Project Manager and S Project Manager and Spark

18 4.3 Meet with Plumbing 1 day Mon 1/3/11 Mon 1/3/11 Project Manager and W Project Manager and Water

19 4.4 Meet with Finish Work 1 day Mon 1/3/11 Mon 1/3/11 Project Manager and W Project Manager and Wood

20 4.5 Meet with Student Workers 1 day Mon 1/3/11 Mon 1/3/11 Project Manager and S Project Manager and Stude

21 5 Electrical Permits 10 days Mon 1/3/11 Fri 1/14/11

22 5.1 Obtain Electrical Permits 10 days Mon 1/3/11 Fri 1/14/11 Sparks Electrical PM Sparks Electrical P

23 6 Plumbing Permits 10 days Mon 1/3/11 Fri 1/14/11

24 6.1 Obtain Plumbing Permits 10 days Mon 1/3/11 Fri 1/14/11 Waterworks Plumbing Waterworks Plumbi

25 7 Building Permits 10 days Mon 1/3/11 Fri 1/14/11

26 7.1 Obtain Building Permits 10 days Mon 1/3/11 Fri 1/14/11 East Side Framing & D East Side Framing

27 8 Framing 15 days Mon 1/3/11 Fri 1/21/11

28 8.1 Framing-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11 East Side Framing & D East Side Framing & Dryw

29 8.2 Framing-Build 15 days Mon 1/3/11 Fri 1/21/11 East Side Framing & D East Side Fra

30 8.3 Framing-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City & County City & County

31 8.4 Framing-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager Project Manager

32 9 Electrical 10 days Mon 1/3/11 Fri 1/14/11

33 9.1 Electrical-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11 Sparks Electrical PM Sparks Electrical PM

34 9.2 Electrical-Install 10 days Mon 1/3/11 Fri 1/14/11 Sparks Electrical Sparks Electrical

35 9.3 Electrical-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City & County City & County

36 9.4 Electrical-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager Project Manager

37 10 Plumbing 10 days Mon 1/3/11 Fri 1/14/11

38 10.1 Plumbing-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11 Waterworks Plumbing Waterworks Plumbing PM

39 10.2 Plumbing-Install 10 days Mon 1/3/11 Fri 1/14/11 Waterworks Plumbing Waterworks Plumbi

Project: District4Move.mpp

Date: Sat 1/8/11

Task Milestone External Tasks Split Summary External Milestone Progress Project Summary Deadline

Page 1

ID WBS Task Name Duration Start Finish Predecessors Resource Names January Februar

2/1 2/2 1/2 1/9 1/16 1/23 1/30 2/6

40 10.3 Plumbing-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City & County City & County

41 10.4 Plumbing-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager Project Manager

42 11 Drywall 15 days Mon 1/3/11 Fri 1/21/11

43 11.1 Drywall-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11 East Side Framing & D East Side Framing & Dryw

44 11.2 Drywall-Install 15 days Mon 1/3/11 Fri 1/21/11 East Side Framing & D East Side Fra

45 11.3 Drywall-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City & County City & County

46 11.4 Drywall-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager Project Manager

47 12 Finish Work 15 days Mon 1/3/11 Fri 1/21/11

48 12.1 Finish-Order Supplies 3 days Mon 1/3/11 Wed 1/5/11 Woodcraft Carpentry P Woodcraft Carpentry PM

49 12.2 Finish-Install 15 days Mon 1/3/11 Fri 1/21/11 Woodcraft Carpentry Woodcraft Car

50 12.3 Finish-Inspect 10 days Mon 1/3/11 Fri 1/14/11 City & County City & County

51 12.4 Finish-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager Project Manager

52 13 Workbenches 15 days Mon 1/3/11 Fri 1/21/11

53 13.1 Workbenches-Order Supplies 2 days Mon 1/3/11 Tue 1/4/11 Student Workers Mana Student Workers Manager

54 13.2 Workbenches-Build 15 days Mon 1/3/11 Fri 1/21/11 Student Workers Student Worke

55 13.3 Workbenches-Quality inspection 2 days Mon 1/3/11 Tue 1/4/11 Project Manager Project Manager

56 13.4 Workbenches-Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager Project Manager

57 14 Equipment Packing 2 days Mon 1/3/11 Tue 1/4/11

58 14.1 Pack production equipment 2 days Mon 1/3/11 Tue 1/4/11 City Equipment Mover City Equipment Movers PM

59 14.2 Pack non-production equipment 2 days Mon 1/3/11 Tue 1/4/11 City Equipment Mover City Equipment Movers

60 14.3 Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager Project Manager

61 15 Move 3 days Mon 1/3/11 Wed 1/5/11

62 15.1 Move production equipment 3 days Mon 1/3/11 Wed 1/5/11 Express Moving Comp Express Moving Company

63 15.2 Move non-production equipment 3 days Mon 1/3/11 Wed 1/5/11 Express Moving Comp Express Moving Company

64 15.3 Project Sign-off 1 day Mon 1/3/11 Mon 1/3/11 Project Manager Project Manager

65 16 Procurement Closure 3 days Mon 1/3/11 Wed 1/5/11

66 16.1 Review contract work 3 days Mon 1/3/11 Wed 1/5/11 Project Manager Project Manager

67 16.2 Release contractors 1 day Mon 1/3/11 Mon 1/3/11 Project Manager Project Manager

68 16.3 Pay contractors 1 day Mon 1/3/11 Mon 1/3/11 Project Manager Project Manager

69 17 Project Closure 3 days Mon 1/3/11 Wed 1/5/11

70 17.1 Final report 3 days Mon 1/3/11 Wed 1/5/11 Project Manager Project Manager

71 17.2 Archive documentation 3 days Mon 1/3/11 Wed 1/5/11 Project Manager Project Manager

72 17.3 Lessons Learned 1 day Mon 1/3/11 Mon 1/3/11 Project Manager Project Manager

Project: District4Move.mpp

Date: Sat 1/8/11

Task Milestone External Tasks Split Summary External Milestone Progress Project Summary Deadline

Page 2