project plan update and powerpoint
Trillo Apparel Company
The Trillo Apparel Company
________________________________________
Project Name: District 4 Production Warehouse Move Project
Project Manager:
Sponsor: CEO of Trillo Apparel Co.
________________________________________
Project objectives
Trillo Apparel Company is working its strategies in order to raise the distribution and sales in the market environment. As a result of the business growth, the management prefers moving the company to a wider area having enough spaces for easy shipping and production. The exercise is seen as a forward way of improving the product quality and production of the company. The company also has a hope to further the recognition of the brand as one of the methods of marketing the name of the company that in turns calls for more clients coupled with revenue increase. The objective of the nutshell is to construct a high-quality warehouse and another aspect of shipping offices and production in 4 months at a cost not exceeding $1 million dollars.
Deliverables
With respect to the company’s vice president, the production and 5the apparel design is estimated to be expanded with sufficient spaces for all the finished appliances in ensuring that the entire production estimate is met. The best plumbing and electricity appliances to be done and the finished warehouse should incorporate drywalls of high quality. A highly sophisticated building should be established within the confines of a good product floor work benches. The warehouse should have an easy access to ensure availability for use void of any problems at the end of the project. In addition, the office is to be expanded with the current use of technology.
Milestone
The approval of the permits should be finished and done in a range of one to three weeks. The poured foundation should be performed in one month while the final inspection performed in one month and accessed after a period of four months with respect to the project. The workday's production is estimated to be in 5 days a week while other inspecting and permitting to be done in three works. All the inspection pertaining mechanical, plumbing, and electrical should be passed following the needed criteria by the standards of construction to allow the construction to have an overall final inspection.
Technical requirements
The technical requirements stipulate that the warehouse must meet all the codes of local building presented in the rules of construction where all the doors and windows fitted must pass the class 40 rate of the energy. The exteriors of the wall insulations of the warehouse must meet the needed standard size for all warehouses. The insulations of the ceiling must meet the "R" factor that is needed by the standards of the construction. The insulation of the floor should be in the needed size factor applicable in all warehouses. All the project structures must meet the seismic codes of stability that are given by the department of construction. In this regard, the warehouse will accommodate enough apparels of production with more spaces inside.
Limits and exclusions
The warehouse is limited in that it will be built in regard to the specifications and design of the original blueprint that were provided by Trillo Apparel Company who is the customers. The owner takes the responsibility of landscaping. In addition, the contractor should reserve the rights to contract services and also held responsible for subcontracted work in the project warehouse. In the project development, the air conditioning in the warehouse is not included though all the pre-wiring is included. The work is limited to a two months period.
Reviews with customer
The scope of the project is to be reviewed by the stakeholders of the project and Trillo Apparel Company. This step gives the prerequisite ensures that the scope of the project statement increases the chances of a successful project.
• SPONSOR APPROVAL: ______________________________________
TRILLO APPAREL COMPANY
TRILLO APPAREL COMPANY