Resource Management

profileBob1431
team_a_risk_management_plan.docx

Team A Risk Management Plan

Course Project

KG Internet Café

Risk Management Plan

Class: MGMT-404

Professor: Richardson

DeVry University

Oct 3rd, 2014

Team A:

Kent Grant Project Manager

Jacob Fejeran Café Design and setup

Heather Alton Permits and Real estate

Gabriel Cambambia Interior Design and Decor

Dave Williams Supplier and Venders.

Project Name:

KG Internet & Coffee Café

Project Description

This project is hoping to bring a first class internet café as well as a one of a kind international coffee and tea café in one. It will feature the highest bandwidth for blazing speeds. Or you can relax with your friends or make new ones while sitting in comfortable seating sipping world class coffees or teas from around the globe. People of all cultures will enjoy the diverse environment that plays tribute to all cultures worldwide with entertainment and events.

Project Manager

Kent Grant

Date:

Oct. 10th, 2014

Revision Number

1

A. Risk Identification

The following is a list of all risk in all areas that could or may cause a delay or disruption in this project. The risk will appear in the Risk Assessment Table.

1. Rental agreement conflict: If the rental agreement is not correct then it could not be signed, therefore delaying the start of the project.

2. Legal issues: This event could cause a delay in the starting of remolding and construction.

3. Permit delays: If not received in and reasonable amount of time this could delay the start date of the project.

4. Condition of the building: This event could increase the cost and time of the project if the building is not in a condition to fit the project’s remolding plan.

5. Labor Unions: In the event of a labor dispute or strike, It will start most major work on the project.

6. Loss of funding: Any loss of funding would result in a delay or stoppage of work brings the project to a stop.

7. Delay of material delivery: Any delay of materials could cause a delay with the step that required the materials, therefore causing a cascading effect for the whole project.

8. Installation of flooring: A delay in completing the installation of the flooring would delay the install of the equipment.

9. Delivery of damaged material: This event may slow the project until replacement pieces can be obtained.

10. Natural events: Depending on the event it could have an adverse effect on the project.

11. Bad communication: Instructions will not smoothly flow up and down the chain of command, resulting in misunderstanding with how things should be done.

12. Improper Preparation: Any misstep in preparations for any step in the projects could impact the timeline of the project.

13. Improper cost analysis: This event could cause a delay with the project as a whole while more funds are procured.

14. Multi-tasking: Lack of focus and incomplete work on assigned task.

15. Team Members: Additional tasks are assigned because a few members abort the project.

16. Building inspection: Not passing building inspection codes can cause a delay with the project timeline.

B. Risk Assessment

The following tables are an assessment of these risks in terms of the probability of project occurrence and the negative cost impact of project outcomes.

RISK SCORING MATRIX

Defined Conditions for Risk Management Analysis

Project

Relative or Numerical Scales

Objective

Very Low - 1

Low - 2

Moderate - 3

High - 4

Very High - 5

Cost

Insignificant

<5% Cost Increase

5-10% Cost

10-20% Cost

> 20% Cost

Cost Increase

Increase

Increase

Increase

Time

Insignificant

Schedule Slippage

Overall Project

Overall Project

Overall Project

Schedule

Slippage

Slippage

Slippage

<5%

Slippage

5-10%

10-20%

>20%

Scope

Scope

Minor Areas of

Major Areas of

Scope

Project End

Decrease

Reduction

Item is

Barely

Scope Affected

Scope Affected

Unacceptable

Effectively

Noticeable

to Client

Useless

Quality

Quality

Only Very

Quality

Quality

Project End

Degradation

Demanding

Reduction

Reduction

Item is

Barely

Applications Are

Requires Client

Unacceptable

Effectively

Noticeable

Affected

Approval

to Client

Unusable

Justification for use of risk scoring matrix

The risk scoring matrix bears benefits to the users. It encourages discussions while being developed. It is from these robust discussions that risks are presented and evaluated critically. The risk scoring matrix helps in prioritizing risks in a consistent manner. The most important benefit of the risk scoring matrix is drawing the attention of decision makers to the risks with the highest priorities.

RISK ASSESSMENT TABLE

Risk

Probability

Cost

Schedule

Scope

Quality

Risk Score

Rental agreement conflict

20%

1

2

2

1

6

Legal issues

10%

1

2

2

1

6

Condition of the building

40%

3

4

3

4

14

Labor Unions

30%

3

4

4

1

12

Permit delays

10%

1

2

2

1

6

Loss of funding

20%

5

5

5

1

16

Delay of material delivery

10%

3

3

3

2

11

Installation of flooring

20%

2

2

1

2

7

Delivery of damaged material

90%

5

4

3

4

16

Natural events

20%

1

1

1

1

4

Bad communication

30%

1

1

1

1

4

Improper Preparation

20%

2

2

1

4

9

Improper cost analysis

30%

5

3

2

1

11

Multi-tasking

20%

1

1

1

1

4

Team Members

10%

1

1

1

1

4

Building inspection

10%

2

3

2

1

8

C. Risk Response

For each risk we have determined the plan of action to be taken if the risk should occur:

accept, shape, reduce, or transfer the risk. The following risk response table identifies a

brief contingency plan for these risks.

RISK RESPONSE TABLE

Risk Event

Response:

Accept,

Reduce,

Share,

Transfer

Contingency Plan

Trigger

Who is Responsible

Loss of funding

Reduce

Be very strict with money allocations

Change in the economy

Heather Alton

Kent Grant

Improper cost analysis

Reduce

Increase estimates by looking at past history projects/documentation

insignificant costs research

Heather Alton

Kent Grant

Condition of the building

Accept

Have funds on stand-by in order to allocate resource to assist with the building

Building inspection and inventory

Kent Grant

Jacob Fejeran

Labor Unions

Reduce

Negotiate independent contract with unions.

Contract termination or expires

Kent Grant

Broken or damaged Material

Share

Order extra items to cover damaged material, research other venders.

Careless handling, accidents in shipping

Dave Williams

Kent Grant

Contingency Plans for the Two Highest Risks

First Highest Risk - Loss of funding for the project

The loss of funding for this project is a very high risk, since this is not a franchise or corporation but an individual endeavor the funding is limited. Any change in the economy or the stakeholders finance would impact the progress of the project. Before the start of the actual project the project manager and all stakeholders will need to meet and draw up strict guidelines as to how the project funds will be allocated so that any saving opportunities that arise can be fully taken advantage of. The methods of allocating any funds are in the below list.

1. Establish a reserve funds in case of any shortfalls.

2. Only the Project manager can release funds for all steps of the project.

3. All steps will be evaluated so that any money saving steps can be taken.

4. There will be no short cuts taken to save funds; all work will meet governmental and stakeholders guidelines.

5. If it looks like fund will run out or low on any steps in the project the Project manager will be notified immediately, He will then contact the stakeholders of the short fall and that money may have to be taken out of the reserve funds.

6. If any funds remain after the completion of a project step those funds will be added to the reserve funds.

Second Highest Risk - Delivery of damaged material

The second highest risk for the project is the delivery of broken or damaged materials. This could delay and alter the timeline in almost every step depending on if the material was for that step of the project. If it accrues then the project team will investigate to see if there can be a work around to another step and return to the step when correct material is obtained. The Supply manager will also be instructing all venders that have to ship material to the site to use the safest and secured method available. In order to help mitigate this risk a small amount of additional item may be ordered to help offset any breakage or damage to order materials. But keeping in mind the funding issues. The following is a list of steps the Supply manager may take to help ensure the safe delivery of all materials.

1. It is a fact that the Supply manager cannot be at every shipping point to inspect the material shipment beforehand, so therefore the Supply manager will be in constant communications with the vender.

2. Will obtain a tracking method and number in order to keep track of all material shipped.

3. Will contract with the vender adjustment to the invoice in the event any of the material arrives in a damaged condition.

4. Will generate a list of venders the carry similar or same material for expedited delivery, depending on the timeline of the step the material is used for.

5. Will arrange the return of any material in returnable condition.

D. Risk Assessment Matrix

All know risk have been analysis in the start of this report. Below is the Risk Assessment Matrix that will show and justify my reasoning to list the Loss of Funds as my first highest risk

Loss of funding

Broken or damaged Material

Likelihood

Condition of the building

Improper cost analysis

Labor Unions

1

2

3

4

5

Impact

Statement of Participation

Kent Grant Project manager Entered data

Sign: Kent Grant

Heather Alton Legal / Finance Supplied Risk Analysis data

Sign: Heather Alton

Jacob Fejeran Café Design and setup Supplied Risk Management Plan data

Sign: Jacob Fejeran

Gabriel Cambambia Internet Design and Décor Supplied Risk Management Plan data

Sign: Gabriel Cambambia

Dave Williams Supplier and Venders. Supplied Risk Analysis data

Sign: Dave William

Version 1: 10/03/2014

7