Research and Analysis of Business Problems

profileyahala
implementation_lecture_rvsd.pdf

BA 301

Research & Analysis of Business Problems

1

Problem Solving 2

Context & Background

Problem Analysis & Description

Solution Development

Evaluation & Decision- Making

Communication & Implementation

Problem Solving 3

Context & Background

Problem Analysis & Description

Solution Development

Evaluation & Decision- Making

Communication & Implementation

The Last Step 4

Project

Management

Plan

Implement

Evaluate

Project Management Questions

 How long will it take to complete the project?

 What individual tasks make up the project and in what order

must they occur?

 Where do we have flexibility in task start and finish dates,

i.e., which tasks can be delayed without affecting the overall

schedule?

 What tasks are “critical” and must be completed exactly as

planned in order to keep on schedule?

 Who is working on which task, and is there any flexibility, if

needed?

 Are we going to be finished on time and on budget?

5

Project Management Tools

 Modern project management software can help

answer these questions:

 Critical Path Method (CPM)

 PERT (Program Evaluation & Review Technique) for task

analysis

 GANTT charts for evaluation and control

 Programs like Microsoft Project combine these

techniques so that projects can be more predictable

and managed more proactively.

6

CPM (Critical Path Method)

 What is the Critical Path?

 It’s the sequence through a set of tasks with the longest

overall duration.

7

How Do The Tools Work?

 They help you organize, manage and control a

project.

 Identify the tasks/activities

 Determine task sequence

 Calculate task lengths

 Graphically present an overview

 And most importantly…

 Work out the critical path

8

Modernize A Shopping Center

Task Code Description Predecessor Time (weeks)

A Prepare architectural drawings None 5

B Identify potential new tenants None 6

C Develop prospectus for tenants A 4

D Select contractor A 3

E Prepare building permits A 1

F Obtain permit approval E 4

G Perform construction D, F 14

H Finalize tenant contracts B, C 12

I Tenants move in G, H 2

Total Time = 51 weeks

Viewing The Plan Visually

 Now you can see which task can be done

concurrently.

A

B

C

E

H

D

I

G

F

Start Finish

10

Critical Path

 Figure out the Critical Path – the longest path through the project.

 Total time can be reduced from 51 weeks to 26 weeks by working concurrently.

A

C

E

H

D

I

G

F

Start Finish

B

11

PERT

 It lets you make an optimistic, pessimistic and “best

guess” estimate of the time it will take for each task

and the entire project.

 Use a weighted average and a formula.

 Plug this timing into the Project Management

Software.

Estimated Time = [(Optimistic x 1) + (Best Guess x 4) + (Pessimistic x1)]/6

Best Guess = 10 weeks

Pessimistic = 14 weeks

Optimistic = 8 weeks

Estimated Time = 10.2 weeks

12

PERT Example

GANTT Charts

 Another way of looking at the relationships between

activities and manipulating dependencies.

14

Microsoft Project 15

Resources

 You must also allocate resources to each of the

activities.

 Who will do it?

 How much will it cost?

 Materials and labor

 Many software packages will allow you to track

progress against budget and manage resource

allocation.

16

Outcome Measurement

 Were we successful, and how do we know?

 Refer back to the cost-benefit analysis:

 If there were quantitative benefits, relate them back to the

analysis.

 If qualitative, questionnaires and interviews can be used to

determine whether they were realized.

 Develop measures to look at short-term and long-term

impacts of the solution.

 Review unexpected outcomes and survey stakeholders.

17

BA 301

Research & Analysis of Business Problems

18

Problem Solving 19

Context & Background

Problem Analysis & Description

Solution Development

Evaluation & Decision- Making

Communication & Implementation

Problem Solving 20

Context & Background

Problem Solving 21

Problem Analysis & Description

Problem Solving 22

Solution Development

Problem Solving 23

Evaluation & Decision- Making

Problem Solving 24

Communication & Implementation

Problem Solving 25

Context & Background

Problem Analysis & Description

Solution Development

Evaluation & Decision- Making

Communication & Implementation