PROBLEM 4 [8 points]
|
Month |
AC |
PV |
EV |
|
5 |
$34 |
$42 |
$39 |
a) Calculate the cost performance index (CPI). [2 points]
CPI= BCWP/ACWP
CPI=39/34= 1.15
b) Is the project cost efficient or not efficient? [2 points]
Efficient
c) Calculate the schedule performance index (SPI). [2 points]
SPI=BCWP/BCWS
SPI=39/42=.93
d) Is the schedule efficient or not efficient? [2 points]
Not efficient
PROBLEM 5 [8 points]
|
Day |
AC |
PV |
EV |
|
65 |
$550 |
$735 |
$678 |
a) Calculate the cost variance (CV). [2 points]
CV=BCWP -ACWP
CV=678-550= 128
b) Calculate the cost performance index (CPI). [2 points]
CPI=BCWP/ACWP
CPI=678/550= 1.2
c) Calculate the schedule variance (SV). [2 points]
SV=BCWP-BCWS
SV=678-735= -57
d) Calculate the schedule performance index (SPI). [2 points]
SPI= BCWP/BCWS
SPI=678/735=.92
e) Given these data, what should a project manager do with respect to this project?
PROBLEM 6 [8 points]
|
Day |
AC |
PV |
EV |
|
65 |
$760 |
$735 |
$678 |
a) Calculate the cost variance (CV). [1 point]
CV=BCWP-ACWP
CV= 678-750= -72
b) Calculate the cost performance index (CPI). [1 point]
CPI=BCWP-ACWP
CPI=678/750=.90
c) Calculate the schedule variance (SV). [1 point]
SV=BCWP-BCWS
SV=678-735 =-57
d) Calculate the schedule performance index (SPI). [1 point]
SPI= BCWP/BCWS
SPI= 678/735=.92
e) Explain the project performance in terms of efficiency, budget, and schedule. What should the project manager do for the project? [4 points]