Using your team's ITP WBS, develop and submit a project risk register in MS Excel:
• A project risk register, from the textbook or its companion Web site, from the classroom material, from www.pmi.org, or from other valid research, that meets the following requirements.
• In MS Excel, the risk register should be populated with the risks for at least 3 tasks of different types and categories at EACH level of the decomposition in the WBS (no fewer than 12 tasks must have risks identified -- 3 major tasks, 3 sub-tasks, 3 lowest level leaf node tasks or sub-sub tasks, and also at least 3 risks at the overall project level (Level 0)). (Note that this is minimum required, along with the other things below, to earn a satisfactory score. To earn a better score, you would want to include more risks at each level, and some of the additional things mentioned below.)
Risks may include, for example, technical IT risks, external risks that impact the project but which are outside the PM's control, project management risks, risks of project changes, and so forth.
• Please note that a task could have more than one risk! The risk register must include MITIGATION strategies to eliminate or minimize the risk (risk handling procedures, mitigations) and contingency plans (what you will do if the risk happens). If the format you are using does not include these columns, please add them, then be clear on the difference between mitigation and contingency. Address what aspect of the project will be affected by each mitigation action - cost, schedule, or scope. Provide a recommendation for whether or not the mitigation action should be implemented, remembering that EACH mitigation will impact the project's scope, cost or schedule.
• The risk register should also include:
o Title or description of item or TASK at risk. (This is the WBS task in which the risk occurs, not the risk itself.)
o Also include the WBS NUMBER to designate which WBS level the task is at. o Description of the RISK (What is the risk? What is at risk of happening?) (This identifies the nature of the risk itself, not the task.)
o Risk category or type (e.g., technical risks, quality risks, financial risks, external risks, organization risks, project risks, quality risks, other risks, etc)
o Consequences, impact, or cost at risk (adjectival or numeric)
o Likelihood or probability (adjectival or numeric)
o Initial risk score (or "risk product", consequence times likelihood)
o Risk handling category (avoidance, mitigation, transfer, acceptance, etc.)
o Risk handling / control / action plan, including a column for each:
the mitigation action that, if taken, would minimize the impact of the risk. (This is MANDATORY – how will you AVOID the risk??)
cost and time to mitigate.
contingency plan - what the team will do if the risk actually happens (This is mandatory – what will you do to minimize harm if the risk happens?).
o See the textbook for definitions and details
o Designation of risk "owner" or risk manager (best designated by title or role rather than by individual's name)
o You should include such things as:
Additional risks
Risks for additional tasks
Results of handling each risk after controls are implemented:
Consequences or cost at risk (Mandatory)
Likelihood or probability (Mandatory)
Final risk score or product (consequence times likelihood) (Mandatory)
Quantitative numerical consequences, probabilities, and risk scores (rather than subjective, qualitative, or adjectival assessments)
Additional narrative discussion of each risk, handling method, etc.
Total of all the risk scores (risk products) for the entire project after risk controls are implemented, in dollars.
Be sure to define terms, especially how you determined risk rankings and risk scores.
o o See the textbook for details
• Also include some risks associated with the general ability to complete the project successfully. (You might consider these risks at Level 0, the root level, of the WBS, affecting the entire project.)
• Finally, if you quantitatively calculated the risk product in those terms, then what is the total of all the initial risk scores (risk products) for the entire project, in dollars.
Questions:
In an accompanying Word doc or text submission, answer the following questions:
1. Which risks (and associated tasks) would be the most threatening to the success of the project and why?
2. Which top THREE mitigations (and associated tasks) and risk handling plans should be implemented, and why? Remember that mitigation actions will affect cost, schedule and/or scope – so discuss what can you AFFORD to do based on the likelihood and impact of the risk?
3. What are the TOTAL impacts on cost, schedule and scope for the project if the recommended risk controls and mitigation actions are taken? If you use costs, how did you calculate the cost? Will the risk handling improve things or make them worse? That is, will the project cost more and/or be less successful because of risk handling, or will it cost less and/or be more successful because of risk handling? How so? Explain.
4. How did you determine those costs and impacts? Please describe. What is the benefit of mitigating risks that are identified for mitigation?
Submit the document(s) in your Assignment Folder.
Approximate breakdown by areas include:
o General: Structure, Format, Mechanics, Style (~5%)
o Risk register (~84%)
o Questions (~10%)
Rubrics and Grading for the ITP-5 Project Deliverable
To earn 90-100% of the points available for this assignment –
The risk register meets the basic requirements. Identify at least 10 risks at each level of the WBS, including risks that affect the general ability to complete the project successfully, major tasks of different types and categories, sub-tasks of different types and categories, risks of several different risk types and categories, including external risks, financial risks, organization risks, PM risks, quality risks, technical risks, and other risk categories. In addition, include such things as:
Multiple risks for single tasks
Quantitative numerical consequences, probabilities, and risk scores (rather than subjective, qualitative, or adjectival assessments)
Show risk assessment (probability, impact, and score) numerically (e.g., percentages, dollars, etc) rather than qualitatively.
Additional narrative discussion of each risk, handling method, etc.
Designation of risk "owner" or risk manager and why that person or functional position is the “owner”
Total of all the risk scores (risk products) for the entire project after risk controls are implemented, in dollars.
Also include some risks associated with the general ability to complete the project successfully. (You might consider these risks at Level 0, the root level, of the WBS, affecting the entire project.)
Answer all the initial risk scores (risk products) for the entire project, in dollars.
Include the following risk info for ea. risk: Title or description of item or TASK at risk; Description of the RISK; Risk category or type; Initial assessment of Consequences, impact, or cost at risk; initial likelihood or probability; Initial risk score (consequence x likelihood); Risk handling CATEGORY; Risk handling / control / mitigation / action PLAN; Designation of risk "owner"; Risk results with/after controls / handling plans implemented (Consequences or cost with controls; Likelihood or probability with controls; Final risk score (consequence x likelihood)). Answer all questions, and include reference sources are used in the text and included in a Reference page. Show risk assessment (probability, impact, and score) numerically (e.g., percentages, dollars, etc) rather than qualitatively.