HELPCLICK monday homework

profilealhajerh
4_cu_time.ppt

Bob Kois PMP MBA

Project Management

Time Management

EPICPM®

*

Time Management

Scope

Time

Resources

Cost

Quality/Technology

*

Time Management

What is Project Time Management?

  • Project Time Management – Includes the processes required to accomplish timely completion of the project.*

*Source: PMBOK® pg 129

*

Time Management

Closing
Process Groups Initiating Planning Executing Monitoring & Controlling Closing
Time Management Knowledge Area Processes Define Activities Sequence Activities Estimate Activity Resources Estimate Activity Duration Develop Schedule Control Schedule

*

Define Activities

  • Define Activities – The process of identifying the specific actions to be performed to produce the project deliverables.”

*Source: PMBOK® p.129

*

A level small enough to estimate, schedule, monitor and manage

Sequence Activities

  • Sequence Activities – The process of identifying and documenting relationships among the project activities.”

*

Sequence Activities

Start to Start

Task A

Task B

Precedence Relationships

Task A & B may start at the same time but (B) can’t begin until the first task (A) has started.

*

The first type of relationship within Precedence Diagramming is a Start to Start.

Task A

Task B

Task A & B may end at the same time but (B) can’t finish until the first task (A) has finished.

Precedence Relationships

Finish to Finish

Sequence Activities

*

Sequence Activities

Start to Finish

Task A

Task B

Task (A) must start before Task(B) can finish. This method is seldom used.

Precedence Relationships

*

Sequence Activities

Finish to Start

Task A

Task B

Task (A) must finish before the next task, task (B) can begin. This is the most common method.

Precedence Relationships

*

Sequence Activities

Task E

Finish

Task F

Task D

Task C

Task B

Task A

Start

Task G

1

2

3

  • Shows a diverging point.
  • C to D shows a finish to finish activity.
  • F to G shows a start to start activity.
  • Shows a converging point

4

Precedence Diagramming

Method (PDM)

*

Here is what a Precedence diagram looks like when you put it all together.

Sequence Activities

  • Schedule Network Templates
  • Dependencies
  • Mandatory (Hard Logic)

Inherent in the nature of the work being done

  • Discretionary (Soft Logic)

Defined by the project management team

  • External

Involve a relationship between project activities and non-project activities

*

The three (3) out of the four (4) tools listed under the tools and techniques are Network Based Schedules. You can think of these schedules as visual representations of the project as they entail boxes or circles and arrows connecting them.

WBS Example

*

Sequence Activities - Gantt Chart

*

Sequence Activities – Network Diagram

*

WBS Controls

WORK

BREAKDOWN

STRUCTURE

MGT.

COORDIN.

ORGANIZ.

CHARTS

COSTS

ACCOUNT-

ABILITY

DECISION

TREES

SCHEDULES

*

Estimate Activity Resources

  • Estimate Activity Resources – Is the process used to estimate the type and quantities of resources (persons, equipment, or material) required to perform each schedule activity.

*

Activity Duration Estimating

  • Uses work periods as the primary measure
  • Answers the question “How long will this activity or deliverable take?”
  • Duration is in terms of calendar time.


Estimate Activity Durations

  • Estimate Activity Durations – The process of approximating the number of work periods it will take to complete individual activities with estimate resources.

*

Activity Duration Estimating

  • Uses work periods as the primary measure
  • Answers the question “How long will this activity or deliverable take?”
  • Duration is in terms of calendar time.

Develop Schedule

  • Schedule Development – The process of analyzing activity sequences, durations resources requirements, and schedule constraints to create the project schedule.

*

Schedule Development gives you the ability to create operating plans to manage the project.

The purpose of the schedule is to convert the project plan into an operating plan that is the basic tool for controlling all project activities.

Develop Schedule

  • Mathematical Analysis
  • Critical Path Method (CPM)
  • Graphical Evaluation & Review Technique (GERT)
  • Program Evaluation & Review Technique (PERT)

*

Within the tools section there are five (5) tools for schedule development. We are going to focus on two (2): PERT and the critical path method.

Time Management

Time Management

Time Management

!"#$%&'"() *+,)+-.+(%/%0+1+-.+(

!"#$%&'"() *+,)+-.+(%/%0+1+-.+(