cost estimation using ms project
Week 6 Home Assignment – Project Estimation – 50 Points
Based on the project estimation information (page 2 – page 6), create the MS Project cost estimation plan.
Requirements
1. (8 pts.) WBS
Create the MS Project WBS with individual tasks, summarizing as appropriate for phases.
2. (34 pts.) Entering the LABOR/WORK ESTIMATES
For each task in the WBS, 3 labor or Work estimates – pessimistic, most likely and optimistic were created. Use the most likely labor estimate for each WBS activity. The minimum Work estimate for a task is 1 hour and the pay rates should be in whole dollar values. The company will pay overload if there are resource overloads
3. (4 pts.) Entering the NON-LABOR/MATERIAL ESTIMATES
4. (4 pts.) Appropriate totals appear on each of the estimate worksheets.
Project Duration Estimate
Project Resource Information
Page 1 of 6
Labor Estimate
Non - Labor Estimate (all non-recurring)
NOTES:
3.3 Implement Marketing Strategy: Advertising material development and publication (electronic, hard copy).
4.1 Develop Prototype: Prototype materials.
5.2 Layout Production Line: Additional hardware/software/tools for enhancement to existing production line.
6.2 Document Customer Support Process: Electronic and hard copy publication costs.
6.3 Train Staff on Customer Support Process: Training materials.
Page 6 of 6
ResourceMax UnitsStd RateOvt Rate
Engineering 1100%$50.00/hr$50.00/hr
Engineering 2100%$50.00/hr$50.00/hr
Engineering 3100%$50.00/hr$50.00/hr
Marketing 1100%$40.00/hr$40.00/hr
Marketing 2100%$40.00/hr$40.00/hr
Marketing 3100%$40.00/hr$40.00/hr
Marketing 4100%$40.00/hr$40.00/hr
Production 1100%$25.00/hr$37.50/hr
Production 2100%$25.00/hr$37.50/hr
Production 3100%$25.00/hr$37.50/hr
Customer Service 1100%$25.00/hr$35.00/hr
Customer Service 2100%$25.00/hr$35.00/hr
Customer Service 3100%$25.00/hr$35.00/hr
Customer Service 4100%$25.00/hr$35.00/hr
Customer Service 5100%$25.00/hr$35.00/hr
Customer Service 6100%$25.00/hr$35.00/hr
Customer Service 7100%$25.00/hr$35.00/hr
Customer Service 8100%$25.00/hr$35.00/hr
Customer Service 9100%$25.00/hr$35.00/hr
Customer Service 10100%$25.00/hr$35.00/hr
Customer Service 11100%$25.00/hr$35.00/hr
Customer Service 12100%$25.00/hr$35.00/hr
Labor Estimate
WBSTask Name
No. of
People
Est
(hrs)
Work
(hrs)
1Define New Product
1.1Brainstorm Product Ideas3824
Engineering188
Marketing188
Production188
1.2Research Brainstormed Product Ideas31648
Engineering11616
Marketing11616
Production11616
1.3Decide on 2 Product Ideas6212
Engineering122
Marketing122
Production122
Engineering122
Marketing122
Production122
2Design New Product
2.1Define Product Requirements340120
Engineering14040
Marketing14040
Production14040
2.2Define Product Design380240
Engineering18080
Marketing18080
Production18080
2.3Review Product Design6424
Engineering144
Marketing144
Production144
Engineering144
Marketing144
Production144
3Market New Product
3.1Develop Marketing Strategy32472
Marketing22448
Marketing12424
3.2Review Marketing Strategy4416
Marketing248
Marketing144
Customer Service144
3.3Implement Marketing Strategy280160
Marketing280160
Most Likely
4Develop New Product
4.1Develop Prototype280160
Engineer280160
4.2Test Prototype23264
Engineer23264
4.3Review Prototype6424
Engineering144
Marketing144
Production144
Engineering144
Marketing144
Production144
4.4Develop Production Model380240
Engineering280160
Production18080
4.5Test Production Model460240
Engineering260120
Production260120
4.6Review Production Model7856
Engineering2816
Production2816
Engineering188
Marketing188
Production188
5Deliver Product in Production
5.1Design Production Process260120
Production260120
5.2Layout Production Line260120
Production260120
5.3Test Production Line24080
Production24080
5.4Review Production Line3824
Production2816
Production188
6Setup Customer Support
6.1Design Customer Support Process260120
Customer Service260120
6.2Document Customer Support Process260120
Customer Service260120
6.3Train Staff on Customer Support Process1016160
Customer Service816128
Customer Service21632
6.4Rollout Customer Support Process12896
Customer Service10880
Customer Service2816
Non-Labor Estimate
Pessimistic
Most Likely
Optimistic
WBS
Task Name
1
Define New Product
1.1
Brainstorm Product Ideas
1.2
Research Brainstormed Product Ideas
1.3
Decide on 2 Product Ideas
2
Design New Product
2.1
Define Product Requirements
2.2
Define Product Design
2.3
Review Product Design
3
Market New Product
3.1
Develop Marketing Strategy
3.2
Review Marketing Strategy
3.3
Implement Marketing Strategy
$150,000
$100,000
$50,000
4
Develop New Product
4.1
Develop Prototype
$1,500
$1,300
$1,000
4.2
Test Prototype
4.3
Review Prototype
4.4
Develop Production Model
4.5
Test Production Model
4.6
Review Production Model
5
Deliver Product in Production
5.1
Design Production Process
5.2
Layout Production Line
$15,000
$10,000
$8,000
5.3
Test Production Line
5.4
Review Production Line
6
Setup Customer Support
6.1
Design Customer Support Process
6.2
Document Customer Support Process
$800
$500
$300
6.3
Train Staff on Customer Support Process
$15,000
$8,000
$5,000
6.4
Rollout Customer Support Process
TOTALS
$182,300
$119,800
$64,300
WBSTask Name
Pessimistic
Duration
(Days)
Most Likely
Duration
(Days)
Optimistic
(Days)Predecessor
1Define New Product
1.1Brainstorm Product Ideas321
1.2Research Brainstormed Product Ideas8651.1
1.3Decide on 2 Product Ideas2111.2
2Design New Product
2.1Define Product Requirements151081.3
2.2Define Product Design2015102.1
2.3Review Product Design2112.2
3Market New Product
3.1Develop Marketing Strategy10532.3
3.2Review Marketing Strategy2113.1
3.3Implement Marketing Strategy3020153.2
4Develop New Product
4.1Develop Prototype2015103.3
4.2Test Prototype10534.1
4.3Review Prototype2114.2
4.4Develop Production Model2015104.3
4.5Test Production Model151084.4
4.6Review Production Model2114.5
5Deliver Product in Production
5.1Design Production Process151084.6
5.2Layout Production Line151085.1
5.3Test Production Line10535.2
5.4Review Production Line2115.3
6Setup Customer Support
6.1Design Customer Support Process151085.4
6.2Document Customer Support Process151086.1
6.3Train Staff on Customer Support Process2015106.2
6.4Rollout Customer Support Process3020166.3