Determine
(a) the cycle time for the first unit in the second batch,(4)
(b) The setback, (3)
(c) The total time to produce the second batch (3)
(d) Bonus Question: The total time to produce the 1st and 2nd batch.( Bonus +2)
Note:
1-Every student will refer to table in the next page in order to get the data for the above problem
2- Your work must be in clear steps using this word file
3-The numbers must be up to 4 decimals and do not forget to write the units for each solution and do not change the units for the question if it is given in minutes your solution must be in minutes.
4- You must write your name, id and serial number in the word file you will submit
5- You submit the solution word file in the web ct
Serial #IDT1DBatch 1Batch 2LR
120084384014516016075
220084912071015212977
320089414088625580
420091473013611113582
5200917490641455676
62009257901471988278
7200936850126817076
820095065013616912983
92009508107411110585
1020098635058818183
1120099171010101475582
122010153809314519975
1320101678085828181
142010179801555911483
152010217001431217584
162010279601256615676
1720103470083688583
1820103610091110413680
192010384209914216482
2020103956015717011785
2120103984011101139976
222010486209101945585
2320104976013311810983
24201058200146597281
25201058340741878485
2620106216014417619178
27201067020836119485
282010693405714111085
2920107052013318310484
3020107454013105919377
3120107458011715714480
322010786801331187275
33201079520986811184
342010802001267018981
35201136030736911378
362011450301541348675
37201145210155667582
382011637101231309678
39201171970731226280
40201183270551978282