FOR Accounting Genius ONLY
1. Duggan Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are expected to total $276,100 for the year, and machine usage is estimated at 125,500 hours.
For the year, $291,988 of overhead costs are incurred and 130,200 hours are used.
Compute the manufacturing overhead rate for the year. (Round answers to 2 decimal places, e.g. 1.25.)
Manufacturing overhead rate $ 2.20 per machine hour
Answer:
Manufacturing Overhead Rate = Estimated Overhead ÷ Estimated Machine Hours
= $276100 ÷ 125500 hours = $2.20 Per Machine Hour
b. What is the amount of under- or over applied overhead at December 31?
Amount $__5548______
Is the amount over applied or under applied? ___Under applied______
c. Prepare the adjusting entry to assign the under- or overapplied overhead for the year to cost of goods sold.
Account Titles and Explanation Debit Credit
_________________ __________ ______________
________________ _____________ ____________________
2. The ledger of Custer Company has the following work in process account.
Work in Process-Painting
|
5/31 Balance 4,600 |
5/31 Transferred out? |
|
5/31 Materials 5,840 |
|
|
5/31 Labor 4,770 |
|
|
5/31 Overhead 1,830 |
|
|
5/31 Balance ? |
|
Production records show that there were 540 units in the beginning inventory, 30% complete, 1,580 units started, and 1,600 units transferred out. The beginning work in process had materials cost of $2,930 and conversion costs of $1,670. The units in ending inventory were 40% complete. Materials are entered at the beginning of the painting process.
(a) How many units are in process at May 31?
Work in process, May 31 520 units
Answer:
|
|
Units |
|
Work in process, May 1 |
540 |
|
Started into production |
1580 |
|
Total units to be accounted for |
2120 |
|
Less: Transferred out |
1600 |
|
Work in process, May 31 |
520 |
(b) What is the unit materials cost for May? (Round unit costs to 2 decimal places, e.g. 2.25.)
The unit materials cost for May $4.14
(c) What is the unit conversion cost for May? (Round unit costs to 2 decimal places, e.g. 2.25.)
The unit conversion cost for May $4.57
(d) What is the total cost of units transferred out in May? (Round answer to 0 decimal places, e.g. 1,225.)
Total Cost = (1600 x 4.14) + (1600 x 4.57) = $13936
(e) What is the cost of the May 31 inventory? (Round answer to 0 decimal places, e.g. 1,225.)
Cost = [(520 x 4.14) + (520 x 4.57)] = $3103
|
|
Equivalent Units |
|||
|
|
|
Materials |
|
Conversion Costs |
|
|
Units transferred out Work in process, May 31 520 X 100% 520 X 40% |
1,600
520 - 2120 |
|
1,600
- 208 1392 |
|
|
Direct Materials |
Conversion Costs |
|
|
$ |
$ |
|
Work in process, May 1 |
2930 |
1670 |
|
Costs added: |
|
|
|
Material |
5840 |
|
|
Conversion costs (4770 + 1830) |
|
6600 |
|
Total Cost (A) |
8770 |
8270 |
|
|
|
|
|
Equivalent Units (B) |
2120 |
1392 |
|
Unit costs ($) (A ÷ B) |
4.14 |
5.94 |
|
|
|
|
3. Wilkins Inc. has two types of handbags: standard and custom. The controller has decided to use a plant wide overhead rate based on direct labor costs. The president has heard of activity-based costing and wants to see how the results would differ if this system were used. Two activity cost pools were developed: machining and machine setup. Presented below is information related to the company’s operations.
Standard Custom
Direct labor costs $53,600 $115,000
Machine hours 1,430 1,490
Setup hours 95 390
Total estimated overhead costs are $301,800. Overhead cost allocated to the machining activity cost pool is $197,800, and $104,000 is allocated to the machine setup activity cost pool.
Compute the overhead rate using the traditional (plant wide) approach. (Round answers to 2 decimal places, e.g. 12.25 %.)
Predetermined overhead rate 179 % of direct labor cost.
Answer:
Predetermined overhead rate = Estimated overhead/ Direct labor costs
= $301,800/ ($53,600 + $115,000)
= 179%
b. Machining $ 67.74 per machine hour
Machine setup $ 214.43 per set up hour
Total machine hours = 1430+1490 = 2,920 hours
Total machine setup hours = 95 + 390 = 485 setup hours
Overhead rates using the activity-based costing approach:
Machining overhead rate = $197800/ 2920 hours = $67.74 per hour
Machine setup overhead rate = $104000/ 485 setup hours = $214.43 per setup hour
C. Determine the difference in allocation between the two approaches. (Round answers to 0 decimal places, e.g. $1,225.)
Traditional costing
Standard $__________
Custom $___________
Activity-based costing
Standard $_____ Custom$_________