Assignment 4
1. Chapter 5, Exercise #2 (page 149). Below is a project WBS with cost apportioned by percents.
a. If the total project cost is estimated to be $600,000, what are the estimated costs for the following deliverables?
· Design?
· Programming?
· In-house testing?
b. What weaknesses are inherent in this estimating approach?