operations
Prob1&2
| Problem 1/2 | |||||
| Activity | Activity Time | Immediate Prd | |||
| A | 3 | none | |||
| B | 4 | A | |||
| C | 2 | B | |||
| D | 5 | B | |||
| E | 4 | C | |||
| F | 3 | D | |||
| G | 2 | E,F | |||
| Use the fill shape tool to identify the critical path | |||||
| 4 | |||||
| 2 | |||||
| 2 | |||||
| 3 | 4 | ||||
| 5 | 3 | ||||
| a | |||||
| b |
a
b
c
d
e
f
g
Prob4-8
| Problem 6 | |||||||||||||||
| #4> | Draw together | ||||||||||||||
| #7> | Completion time | ||||||||||||||
| Critical path | acegij | ||||||||||||||
| #8> | Standard Deviation | 0 | |||||||||||||
| 38 | P(project<38wks) | 38 | |||||||||||||
| 42 | P(project<42wks) | 42 | |||||||||||||
| = normdist(x,mean,sdev,1) | |||||||||||||||
| Activity | Immediate Prd | Optimistic Time | Most Likely Time | Pessimistic Time | (#5) Expected Time | (#6) Variance | |||||||||
| A | none | 3 | 6 | 9 | |||||||||||
| B | A | 3 | 5 | 7 | |||||||||||
| C | A | 4 | 7 | 12 | |||||||||||
| D | B | 4 | 8 | 10 | |||||||||||
| E | C | 5 | 10 | 16 | |||||||||||
| F | D,E | 3 | 4 | 5 | |||||||||||
| G | D,E | 3 | 6 | 8 | |||||||||||
| H | F | 5 | 6 | 10 | |||||||||||
| I | G | 5 | 8 | 11 | |||||||||||
| J | H,I | 3 | 3 | 3 | Possible Paths | ||||||||||
| Path1 | Path2 | Path3 | Path4 | ||||||||||||
| Total Time |
a
b
e
f
g
j
h
d
i
c
Prob10
| Problem 10 | ||||||
| 1.Determine how much the project needs to be reduced | ||||||
| 2. Determine which activities on the critical path can be reduced | ||||||
| 3. Crash critical activities on the basis of increasing costs | ||||||
| Crash the least expensive activity first and so on | ||||||
| Calculate the total costs associated with crashing the project | ||||||
| Crash this project by 3 weeks | ||||||
| Activity | Normal Time | Normal Cost | Crash time | Crash Cost | Max Weeks Reduced | Crash Cost per Week |
| A | 4 | $ 800 | 3 | $ 1,200 | 1.0 | $ 400 |
| B | 3 | $ 900 | 2 | $ 1,000 | 1.0 | $ 100 |
| C | 5 | $ 1,250 | 3 | $ 2,250 | 2.0 | $ 500 |
| D | 2 | $ 800 | 2 | $ 800 | 0.0 | $ - 0 |
| E | 5 | $ 1,500 | 4 | $ 2,000 | 1.0 | $ 500 |
| F | 6 | $ 2,000 | 5 | $ 3,000 | 1.0 | $ 1,000 |
| G | 4 | $ 600 | 3 | $ 900 | 1.0 | $ 300 |
| H | 3 | $ 900 | 3 | $ 900 | 0.0 | $ - 0 |
| Activity | Savings | |||||
| Take one week from | ||||||
| Take one week from | ||||||
| Take one week from | ||||||