i need help in making a powerpoint presentation describing a specific street.
Project Overview MARCH 27, 2013
EXAMPLE PRESENTATION
UNIVERSITY OF TEXAS AT SAN ANTONIO
JOHN W. STRYBOS, P.E.
Sunday, April 6, 14
1
CE 1403 EXAMPLE PRESENTATION
4/6/14
1
Site location
Sunday, April 6, 14
2
CE 1403 EXAMPLE PRESENTATION
Project Goals
Sunday, April 6, 14
3
CE 1403 EXAMPLE PRESENTATION
4/6/14
3
Cost estimates for street, drainage and utilities
Prepare cost estimates, narrative and presentation.
Understand the basics of how Civil Engineers Communicate.
Description
Describe your project.
Use the following slides to discuss status, schedules, budget, etc.
For more info . . .
List location or contact for specification (or other related documents)
Sunday, April 6, 14
4
CE 1403 EXAMPLE PRESENTATION
4/6/14
4
Summary cost estimate
| Category | Cost |
| Construction | $ 2,375,886 |
| Design | $ 260,414 |
| Waterline | $522,856 |
| Sanitary Sewer | $55,791 |
| Total Cost | $ 3,214,947 |
Sunday, April 6, 14
5
CE 1403 EXAMPLE PRESENTATION
Cost estimates comments (notes)
Prepared cost estimates for streets, drainage, water line, and sanitary sewer line.
The cost estimate is very detailed, but has additional items that need to adjusted for the final group project cost estimate.
For example, the drainage quantity estimates were very approximate.
Sunday, April 6, 14
6
CE 1403 EXAMPLE PRESENTATION
Schedule
Sunday, April 6, 14
7
CE 1403 EXAMPLE PRESENTATION
| Task Name | Duration | Start | Finish | Predecessors |
| START PROJECT | 0 days | Mon 1/7/13 | Mon 1/7/13 | |
| MOBILIZATION | 5 days | Mon 1/7/13 | Fri 1/11/13 | 1 |
| SITE WORK | 10 days | Mon 1/14/13 | Fri 1/25/13 | 2 |
| WATER LINE CONSTRUCTION | 85 days | Mon 1/28/13 | Fri 5/24/13 | 3 |
| SANITARY SEWER CONSTRUCTION | 80 days | Mon 1/28/13 | Fri 5/17/13 | 3 |
| GAS CONSTRUCTION | 80 days | Mon 1/28/13 | Fri 5/17/13 | 3 |
| ELECTRICTIY AND TELECOM | 80 days | Mon 1/28/13 | Fri 5/17/13 | 3 |
| STORM SEWER | 75 days | Mon 1/28/13 | Fri 5/10/13 | 3 |
| STREET CONSTRUCTION | 135 days | Mon 5/27/13 | Fri 11/29/13 | 3,14,24,34,44 |
| HOUSE CONSTRUCTION#1 | 45 days | Mon 12/2/13 | Fri 1/31/14 | 63 |
| HOUSE CONSTRUCTION#2 | 45 days | Mon 12/16/13 | Fri 2/14/14 | 69 |
| HOUSE CONSTRUCTION#3 | 45 days | Mon 12/30/13 | Fri 2/28/14 | |
| HOUSE CONSTRUCTION#4 | 45 days | Mon 1/13/14 | Fri 3/14/14 | |
| HOUSE CONSTRUCTION#5 | 45 days | Mon 1/27/14 | Fri 3/28/14 | |
| HOUSE CONSTRUCTION#6 | 45 days | Mon 2/10/14 | Fri 4/11/14 | |
| HOUSE CONSTRUCTION#7 | 45 days | Mon 2/24/14 | Fri 4/25/14 | |
| HOUSE CONSTRUCTION#8 | 45 days | Mon 3/10/14 | Fri 5/9/14 | |
| HOUSE CONSTRUCTION#9 | 45 days | Mon 3/24/14 | Fri 5/23/14 | |
| PROJECT COMPLETE | 0 days | Fri 5/23/14 | Fri 5/23/14 | 252,232 |
4/6/14
7
Current Status as of APRIL 3, 2013
Sunday, April 6, 14
8
CE 1403 EXAMPLE PRESENTATION
4/6/14
8
Individual project is complete.
Starting Group project.
Delays resulting from learning how to construction documents (plan and profile sheets).
ID
Task
Mode
Task Name
S
M
T
W
T
F
S
S
M
T
W
T
F
S
S
M
T
W
Oct 28, '12
Nov 4, '12
Nov 11, '12