Powerpoint Presentation - Operations and Supply Chain
McGraw-Hill/Irwin
Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved
Chapter 18
Material Requirements Planning
18-*
Learning Objectives
Describe what MRP is and where it is best applied.
Understand the source of the information used by the system.
Demonstrate how to do an MRP “explosion.”
Explain how order quantities are calculated in MRP systems.
18-*
Enterprise Resource Planning and Material Requirements Planning
- Enterprise resource planning (ERP): a computer system that integrates application programs in accounting, sales, manufacturing, and the other functions in a firm
- Materials requirements planning (MRP): a means for determining the number of parts, components, and materials needed to produce a product
MRP provides time scheduling information specifying when each of the materials, parts, and components should be ordered or produced
Dependent demand drives MRP
LO 1
18-*
Master Production Scheduling
- The master schedule deals with end items and is a major input to the MRP process
- All production systems have limited capacity and limited resources
The aggregate plan provides the general range of operation, the master scheduler must specify exactly what is to be produced
- To determine an acceptable feasible schedule to be released to the shop, trial master production schedules are run through the MRP program
LO 1
18-*
Demand for Products
Customers who have placed specific orders
Generated by sales personnel
Orders carry promised delivery dates
No forecasting of these orders
Forecasted demand
Normal independent-demand sales
Demand for parts and components
Spares and repair
LO 2
18-*
Bill of Materials
- Bill of materials (BOM): contains the complete product description, listing the materials, parts, and components along with the sequence in which the product is created
One of the three main inputs to the MRP program
- Often called the product structure file or product tree because it shows how a product is put together
LO 2
18-*
MRP Computer Program
- MRP program uses information from:
Inventory records
Master schedule
Bill of materials
- Process of calculating exact requirements for each item is referred to as the explosion process
Work from top level down in BoM
Consider on-hand balances and scheduled orders
LO 2
18-*
MRP Explosion Process
The requirements for end items are retrieved from the master schedule
These are referred to as “gross requirements” by the MRP program
Uses on-hand balance with schedule of orders to calculate the “net requirements”
Using net requirements, it calculates when orders should be received to meet these requirements
LO 3
18-*
MRP Explosion Process Continued
Find a schedule for when orders are actually released
To account for lead time
Move to level 1 items
Gross requirements for each level 1 item are calculated from the planned-order release schedule for the parents of each level 1 item
Net requirements, planned-order receipts, and planned-order releases are calculated as described in steps 2–4
Repeat for all items in bill of materials
LO 3
18-*
Economic Order Quantity
- Calculate reorder quantity based on EOQ
- EOQ was not designed for a system with discrete time periods such as MRP
- The lot sizes generated by EOQ do not always cover the entire number of periods
LO 4
18-*
Least Total Cost
- Least total cost method (LTC): a dynamic lot-sizing technique that calculates the order quantity by comparing the carrying cost and the setup costs for various lot sizes and then selects the lot in which these are most nearly equal
- Influenced by the length of the planning horizon
LO 4
18-*
Least Unit Cost
- Least unit cost method: a dynamic lot-sizing technique that adds ordering and inventory carrying cost for each trial lot size and divides by the number of units in each lot size, picking the lot size with the lowest unit cost
LO 4