Project Priority Matrix

Constrain Enhance Accept
Scope Yes
Time Yes
Budget Yes

Risk Scoring Template

Defined Conditions for Risk Management Analysis
Project Objective Relative or Numerical Scales
Very Low - 1 Low - 2 Moderate - 3 High - 4 Very High - 5
Cost Insignificant Cost Increase < 3% Cost Increase 3-5% Cost Increase 5-7% Cost Increase > 7% Cost Increase
Time Insignificant Schedule Slippage Schedule Slippage <5% Overall Project Slippage 5-10% Overall Project Slippage 10-20% Overall Project Slippage >20%
Scope Scope Decrease Barely Noticable Minor Areas of Scope Affected Major Areas of Scope Affected Scope Reduction affecting business plan Coffee Shop is unviable
Quality Quality Degradation Barely Noticable Some customer compliants Cust dissatifaction increases daily sales reducing Poor sales.. Business unviable

Risk Mgmt Analysis Template

Risk Management Analysis TEMPLATE
RISK EVALUATION
Risk Probability Cost Schedule Scope Quality Risk Score
1 Delay in Municpal License 70% 4 4 1 1 7.0
2 Delay in signing of Lease deed for property for Coffee Shop 50% 4 4 1 1 5.0
3 Delay in finalising Eqpt vendor 30% 3 4 2 2 3.3
4 Delay in finalsing Pastry supplier 20% 4 1 4 4 2.6
5 Customer tastes for Pastry 20% 2 1 4 3 2.0
6 WiFi Infra availability 20% 1 1 1 3 1.2
7 Labor Unions 10% 4 2 1 3 1.0
8 WiFi Expenses 10% 4 1 1 4 1.0
9 Changes in Tax structure 10% 5 1 1 2 0.9
10 Delay in getting addl Power sanction for 2 Coffee makers & Chiller for pastry 5% 3 5 1 2 0.6

Risk Response Template

Risk Response Matrix
Risk Event Response* Contingency Plan Trigger Person Responsible
1 Delay in signing of Lease deed for property for Coffee Shop Reduce Redo Lease with another landlord Lease not signed by mmddyy PM
2 Delay in finalising Eqpt vendor Accept Look for Temp License for Open air café License not rxd by mmddyy PM
3 Delay in finalsing Pastry supplier Transfer Evaluate another vendor Vendor not finalised by mmddyy PM
4 Customer tastes for Pastry Transfer Evaluate another vendor Vendor not finalised by mmddyy PM
5 WiFi Infra availability Reduce Negotiate with Union Stop work PM
6 Labor Unions Transfer Evaluate another vendor Vendor not finalised by mmddyy PM
7 WiFi Expenses Accept Operate only 1 Coffe Maker & Chiller Sanction not rxd by mmddyy PM
8 Changes in Tax structure Transfer Educate customer on taxes & hence price increase Budgetary provisions PM
9 Delay in getting addl Power sanction for 2 Coffee makers & Chiller for pastry Transfer Look for more choices Cust feedback on pastry flavours PM
10 0 Reduce WiFi Usage tied to Coffee Billing High usage of wifi but less coffee sales PM
* = Eliminate, Mitigate, Share, Transfer, Accept