operations management excel problems

profilewmashles88
ch2hmwk.xlsx

2-P2

Chapter 2-Problem 2
Productivity Ratios
Week 1 3 houses 5 days 0.600 houses/day
Week 2 2 houses 4 days 0.500 houses/day
Productivity=Ouput/Input

Chapter 2 Solutions-&A

&P of &N

2-P4

Chapter 2-Problem 4
Productivity Ratios
Facility 1 240 chairs 6 workers 40.0 chairs/wkr
Facility 2 210 chairs 4 workers 52.5 chairs/wkr
Productivity=Ouput/Input

Chapter 2 Solutions-&A

&P of &N

2-P6

Chapter 2-Problem 6
Productivity Ratios
Old process 60 pieces 1 day
Defects 10 pieces 1 day defect/day
Total produced 50 pieces 1 day pieces/day
New process 90 pieces 1 day
Defects 1 pieces 1 day defect/day
Total produced 89 pieces 1 day pieces/day
Change in Productivity increase in productivity
Change in Defects decrease in defects

Chapter 2 Solutions-&A

&P of &N

2-P8

Chapter 2-Problem 8
Cost per patient patient
Labor $ 15 patient
Materials $ 20 patient
Overhead $ 20 patient
Multifactor Productivity 1.09 (Markup is ~9% over costs)
Labor Productivity $ 60.00 dol 3 hours $ 20.00 per hr

Chapter 2 Solutions-&A

&P of &N