I expect to see an SDLC in Stage 5 even if you are not developing any software but installing off-the shelf. I have received a good question from Tony. You have analyzed (remember your Business Environment Analysis), and your current AS-IS process decomposition. You have also designed your to be process and how the system will look like  (even if you use pre-made applications). Under Design you will need to list the major components of your design that you have spent time either designing or selecting. Development is everything you need to do, prepare before installing the system, etc...I hope you are getting it. Please let me know if you have any questions.

Also about the Schedule , I realize the Walmart Example did not give you an example of a schedule but just stated what needed be in there.

1. A detailed Schedule will be established by the Project Manager for WERP based on planning that will be completed  by the development team. 

2. It will include all required activities that will lead to project success. 

3. It will include the detailed actions required by the steps of the SDLC and identify deliverables and dates that they must be completed.

 

Example of Schedule

Task

Start Date

Completion Date

Project Planning

November 25, 2013

January 1, 2014

 Planning Analysis

December 5, 2013

January 1, 2014

Designing

December 15, 2013

January 1, 2014

 

Manager Meeting

January 15, 2014

January 15, 2014

Review of Vendor Contracts

January 17,  2014

January 22, 2014

Staff Meeting

January 18, 2014

January 18, 2014

QuickBooks

February 3, 2014

February 8, 2014

Social Media

February 5, 2014

 

February 13, 2014

 

Customer discount and reward

February 5, 2014

February 12, 2014

Direct TV

February 5, 2014

February 5, 2014

System testing

February 6, 2014

February 7, 2014

Completion of Project

February 10, 2014

 

February 10, 2014

 

 Training of  the staff

Staff being trained on all computer systems and latest

Technology for the Deli

ongoing

Financing

Loan

 

Small Business Management

Training of the management team and scheduling of meetings

ongoing