ID: Task List: Duration: Predecessors: Resources:

1 Westwood Project 0d

2 Contract Design 1

3 Customer selections 1w 1 ` Sales[25%]

4 Write specifications 1d 3 Specifications

5 Write contract 3h 4 Counsel

6 Plans 12d 5 Drafting[50%]

7 Signatures 1h 6FS+3d Sales

8 Contract begins 0d 7

9 Foundation Stage

10 Excavation 1d 8FS+3d Excavation Contractor

11 Footing/foundation 8d 10 Excavation Contractor

12 Water service 1d 11 Water utility

13 Electrical service 1d 11 Electric Utility

14 Inspection 1h 13FS+1d Building Inspector, PF

15 Foundation stage complete 0d 14

16 Framing Stage 15

17 Wood framing 15d 14 Framing Crew[700%]

18 Roofing 4d 17 Framing Crew[500%]

19 Plumbing 3d 17 Mech/Plumb Contractor

20 Electrical wiring 3d 17 Electrical Contractor

21 Inspection 1h 19,18,20 Building Inspector, PF

22 framing stage complete 0h 21

23 Finishing Stage 22

24 Wallboard 1w 22 Wallboard Crew[500%]

25 Stairway 4d 22 Finish Carpenters

26 Painting 1w 24 Paint crew[800%]

27 Trim 1w 26SS+33% Finish Carpenters

28 Landscaping 4d 27

29 Customer walk through 3h 26FS+2d,27

30 Punch list corrections 4d 29

31 Final inspection 1.5h 30,28 Building Inspector, PF

32 Finishing stage complete 0d 31

33 Close-out Stage 32

34 Administrative closure 1d 32

35 Project complete 0d 34