TEXAS DEPARTMENT OF INFORMATION RESOURCES

Project Plan

Template

Version 2.0 ● 30 MAY 2008

image1.png

Using this Template

The companion tool, Project Plan Instructions, provides detailed direction for completing this template. This and other Framework tools are available online at www.dir.state.tx.us/pubs/framework/.

To create a deliverable from this template:

1. Delete the template title page (previous page) and this page.

2. Replace [bracketed text] on the cover page (next page) with your project and agency information.

3. Replace [bracketed text] in the tool header area at the top of page i (Contents page) with the same project and agency information as on the cover page.

Note: Please do not remove or modify content in the footer area.

4. Complete the entire template. Each section contains abbreviated instructions, shown in italics, and a content area. The content area is marked with a placeholder symbol (() or with a table. Relevant text from other project deliverables may be pasted into content areas.

Note: Please do not remove the italicized instructions.

5. Update the table of contents by right-clicking and selecting “Update Field,” then “Update entire table.”

TEXAS PROJECT DELIVERY FRAMEWORK

image2.pngPROJECT PLAN

[Agency/Organization Name]

[PROJECT NAME]

VERSION: [VERSION NUMBER]

REVISION DATE: [DATE]

Approval of the Project Plan indicates an understanding of the purpose and content described in this deliverable. Approval of the Project Plan constitutes approval of the project planning results and hereby certifies the overall accuracy, viability, and defensibility of the content and estimates. By signing this deliverable, each individual agrees the project has been planned effectively as described herein.

Agency Head

[Name]

[Email]

[Telephone]

Signature

Date

Executive Sponsor

[Name]

[Email]

[Telephone]

Signature

Date

Technology Sponsor

[Name]

[Email]

[Telephone]

Signature

Date

Project Manager

[Name]

[Email]

[Telephone]

Signature

Date

Information Security Officer

[Name]

[Email]

[Telephone]

Signature

Date

Contents

1Section 1. Project Overview

11.1 Project Description

11.2 Project Scope

11.3 Assumptions

21.4 Constraints

3Section 2. Project Organization

32.1 Project Structure

32.2 External Stakeholders

32.3 Roles and Responsibilities

4Section 3. Project Start-Up

43.1 Project Life Cycle

43.2 Methods, Tools, and Techniques

43.3 Estimation Methods and Estimates

43.4 Work Activities

53.5 Schedule Allocation

53.6 Resource Allocation

63.7 Budget Allocation

7Section 4. Monitoring and Control

74.1 Change Management

74.2 Issue Management

74.3 Status Reporting

8Section 5. Quality Management

85.1 Quality Management Approach

85.2 Quality Objectives and Standards Identification

85.3 Project Reviews and Assessments

95.4 Deliverables Acceptance Criteria

95.5 Process Improvement Activities

10Section 6. Communication Management

106.1 Communication Management Approach

106.2 Communication Stakeholders and Information Identification

106.3 Distribution Groups

11Section 7. Configuration Management

117.1 Configuration Management Approach

117.2 Configuration Management Tools, Environment, and Infrastructure

117.3 Configuration Identification

117.4 Configuration Control

117.5 Status Accounting and Reporting

117.6 Audits and Reviews

117.7 Interface Control

127.8 Vendor Control

13Section 8. Performance Management

138.1 Performance Management Approach

138.2 Performance Objectives and Standards Identification

14Section 9. Risk Management

149.1 Risk Management Approach

149.2 Risk Assessment

159.3. Risk Monitoring and Control

16Section 10. Project Transition

1610.1 Closeout Plan

1610.2 Phase Closeout

17Section 11. References

18Section 12. Glossary

19Section 13. Revision History

20Section 14. Appendices

Section 1. Project Overview

1.1 Project Description

Describe the approach the project will use to address the business problem, including summarizing how the project will deliver the expected business outcomes and performance objectives.

(

1.2 Project Scope

Describe the project scope by defining what the project will and will not accomplish. Provide a narrative or bulleted list of deliverables, services, and/or solutions expected as outcomes of the project.

Project Includes

Project Excludes

1.3 Assumptions

Describe any project assumptions related to business, technology, resources, scope, expectations, or schedules.

Assumptions

1.4 Constraints

Describe the limiting factors, or constraints, that restrict the project team’s options regarding scope, staffing, scheduling, and management of the project.

Constraints

Section 2. Project Organization

2.1 Project Structure

Describe the organizational structure of the project team and stakeholders, preferably providing a graphical depiction as shown by the example project organization chart in the instructions.

(

2.2 External Stakeholders

Specifically describe external project stakeholders by identifying the stakeholder’s function and interest. A Project Contact Register or its equivalent is developed as part of this section.

Function Stakeholder Represents

Stakeholder Interest

2.3 Roles and Responsibilities

Describe roles and responsibilities for the project structure and external stakeholders as identified above. A Project Contact Register or its equivalent is developed as part of this section.

Role

Responsibility

Section 3. Project Start-Up

3.1 Project Life Cycle

Specify and describe life cycle model(s) that will be used for the project. If formal standards have been established at the organization or agency level, refer to the agency and/or organizational practices. In the description, include tailoring of any practices to accommodate specific project needs if applicable.

(

3.2 Methods, Tools, and Techniques

Identify the method(s), standards, policies, procedures, programming language(s), reusable code repositories, and other notations, tools, and techniques that may be used to develop and/or deploy the products and/or services for the project.

(

3.3 Estimation Methods and Estimates

Describe the methods used to estimate the project level of effort, schedule, and budget. Include tools and techniques used to obtain the estimates in the description. Provide estimates for the project dimensions (effort, schedule, and budget), and identify the source or basis of the estimates and the level of uncertainty and risk associated with the estimates.

Estimation Methods and Estimates

Description

Effort in person-months or person-hours

Schedule in calendar months

Budget in dollars

Source/Basis of Estimates

Level of Uncertainty

3.4 Work Activities

Provide a reference to the location of the work breakdown structure (WBS) and work packages within the WBS.

WBS Location

3.5 Schedule Allocation

Provide a reference to the location of the project schedule.

Project Schedule Location

To highlight major accomplishments as initially planned in the project schedule, identify major project milestones and planned completion dates for delivery. This list should reflect products and/or services delivered to the end user as well as the delivery of key project management or other project-related work products.

Major Milestone/Deliverable

Planned Completion Date

3.6 Resource Allocation

Provide a reference to the location of the resource schedule.

Resource Schedule Location

Identify the total number of resources (e.g., personnel, equipment, facilities) that will be needed for the project, For personnel, include each of the defined project organizational roles in the resources and describe skill set requirements when appropriate. Identify the estimated timeframe (start to finish) for project commitment.

Resource

Total

Skill Set Requirements

Timeframe

3.7 Budget Allocation

Provide a reference to the location of the budget schedule.

Budget Schedule Location

Identify the budget amount allocated by key budget category (e.g., project milestone or standard cost categories such as personnel, travel), including the time period that may constrain use of the budget.

Key Budget Category

Budget Amount

Time Period

Section 4. Monitoring and Control

4.1 Change Management

Describe the process for managing all proposed changes, including how change requests are initiated, logged and tracked, and assigned for analysis and recommendation. Include the change request review process and any additional processes. If formal change management policies and procedures have been established at the organization or agency level, refer to the agency and/or organizational practices. In the description, include tailoring of any practices to accommodate specific project needs if applicable.

(

4.2 Issue Management

Describe the process for managing project issues, including the resources, methods, and tools to be used to report, analyze, prioritize, and resolve project issues. Include how the issues will be tracked and managed to closure. If formal issue management policies and procedures have been established at the organization or agency level, refer to the agency and/or organizational practices. In the description, include tailoring of any practices to accommodate specific project needs if applicable.

(

4.3 Status Reporting

Describe how project status reporting information will be used to monitor and control the project, including escalation procedures and thresholds that may be used in response to corrective actions identified as part of the reporting process. If formal status reporting policies and procedures for monitoring and controlling projects have been established at the organization or agency level, refer to the agency and/or organizational practices. In the description, include tailoring of any practices to accommodate specific project needs if applicable.

(

Section 5. Quality Management

5.1 Quality Management Approach

Describe the overall, high-level approach to quality management based on project performance. Summarize how quality management activities will be accomplished collectively. If formal quality management policies and procedures have been established at the organization or agency level, refer to the agency and/or organizational practices. In the description, include tailoring of any practices to accommodate specific project needs if applicable.

(

5.2 Quality Objectives and Standards Identification

Based on project-specific methods, describe how quality objectives and standards are identified and organized in preparation for executing quality management. A Quality Register or its equivalent is developed as part of this section.

(

5.3 Project Reviews and Assessments

Describe the types of project reviews that are directly related to project quality. Describe the quality tools used, frequency, reviewer(s), and the report that will be generated as a result of the review.

Review Type

Frequency

Tools

Reviewer

Reports

Describe how the results of project reviews will be monitored, evaluated, and how variance to acceptable criteria will be reported and resolved.

(

5.4 Deliverables Acceptance Criteria

For each project deliverable, describe the final approval process for acceptance from an overall quality perspective and the objective criteria to be used for stakeholder acceptance.

Deliverable

Final Approval Process

Stakeholder Acceptance Criteria

5.5 Process Improvement Activities

Describe the activities that will be performed periodically to assess the project’s processes, identify areas for improvement, and implement improvement plans.

(

Section 6. Communication Management

6.1 Communication Management Approach

Describe the overall, high-level approach to communication management for the project. Summarize how communication management activities will be accomplished collectively. If formal communication management policies and procedures have been established at the organization or agency level, refer to the agency and/or organizational practices. In the description, include tailoring of any practices to accommodate specific project needs if applicable.

(

6.2 Communication Stakeholders and Information Identification

Based on project-specific methods, describe how project stakeholders and information requirements are identified and organized in order to ensure timely and appropriate collection, generation, dissemination, storage, and ultimate disposition of project information among project stakeholders. A Communication Register or its equivalent is developed as part of this section.

(

6.3 Distribution Groups

Provide a reference to the location of the project distribution list information, or identify and describe distribution groups that will be used to distribute project information, including name and owner.

Project Distribution List Information

Distribution Group Name

Distribution Group Description

Owner

Section 7. Configuration Management

7.1 Configuration Management Approach

Describe the overall, high-level approach to configuration management (CM) for the project. Summarize how configuration management activities will be accomplished collectively. If formal configuration management policies and procedures have been established at the organization or agency level, refer to the agency and/or organizational practices. In the description, include tailoring of any practices to accommodate specific project needs if applicable.

(

7.2 Configuration Management Tools, Environment, and Infrastructure

Describe the tools, environment, and infrastructure required for the execution of the project CM activities.

(

7.3 Configuration Identification

Based on project-specific methods, describe the methods for identifying project configuration items (CI) and for placing CIs of the identified baselines under control. A Configuration Items Register or its equivalent is developed as part of this section.

(

7.4 Configuration Control

Based on project-specific methods, describe how configuration control is imposed on the baselined configuration items.

(

7.5 Status Accounting and Reporting

Describe the configuration status accounting and reporting activities.

(

7.6 Audits and Reviews

Describe the configuration audits and reviews to be held for the project’s CIs.

(

7.7 Interface Control

Describe the interface control activities required to coordinate changes among the project’s CIs and interfacing items outside the scope of the project. Include the external items to which the project’s CIs interface.

(

7.8 Vendor Control

Describe the activities required to incorporate acquired CIs and CIs for which a vendor has responsibility into the environment. Include activities for coordinating changes to these CIs with their appropriate organizations. Describe the CIs for which the vendor has responsibility and the acquired CIs.

(

Section 8. Performance Management

8.1 Performance Management Approach

Describe the overall, high-level approach to product and/or service performance management. Summarize how performance management activities will be accomplished collectively. If formal performance management policies and procedures have been established at the organization or agency level, refer to the agency and/or organizational practices. In the description, include tailoring of any practices to accommodate specific project needs if applicable.

(

Describe the scope of the performance management effort in relation to the project. The performance scope defines limits in terms of managing the performance of the goods and/or services.

(

8.2 Performance Objectives and Standards Identification

Based on project-specific methods, describe how performance objectives and standards are identified and organized in preparation for executing performance management. A Performance Register or its equivalent is developed as part of this section.

(

Section 9. Risk Management

9.1 Risk Management Approach

Describe the overall, high-level approach to risk management for the project. Summarize how risk management activities will be accomplished collectively. If formal risk management policies and procedures have been established at the organization or agency level, refer to the agency and/or organizational practices. In the description, include tailoring of any practices to accommodate specific project needs if applicable.

(

9.2 Risk Assessment

9.2.1 Risk Identification

Based on project-specific methods, describe how risks are identified and organized in preparation for performing risk analysis, such as use of methods and techniques like brainstorming, interviews, and risk factor tables. A Risk Register or its equivalent is developed as part of this section.

(

9.2.2 Risk Analysis

Based on project-specific methods, describe how risks will be analyzed to establish the project exposure for each risk and to determine which risks are the most important ones to address. Describe scales for rating risks and risk threshold values.

Risk Analysis Description

Scales Description

Risk Threshold Values Description

9.2.3 Risk Response Strategies

Based on project-specific methods, describe how risk response strategies are assigned for each risk.

(

9.3. Risk Monitoring and Control

9.3.1 Risk Tracking

Based on project-specific methods, describe how risks will be continually tracked to ensure that effective risk management is performed, such as use of methods and techniques like risk checklists and watch lists.

(

9.3.2 Risk Reporting

Based on project-specific methods, describe techniques to review and present the status of project risks, such as use of reports for examination of risk response strategies in a summarized (collection or risk items) or detailed (single risk item) manner.

(

Section 10. Project Transition

10.1 Closeout Plan

Summarize the plan for closing the project from an administrative, financial, and logistical perspective.

(

10.2 Phase Closeout

Describe phase closeout plans if applicable.

(

Section 11. References

Provide a list of all documents and other sources of information referenced in the Plan and utilized in the project. Include for each the document number, title, date, and author.

Document No.

Document Title

Date

Author

Section 12. Glossary

Define all terms and acronyms required to interpret the Project Plan properly.

(

Section 13. Revision History

Identify changes to the Project Plan.

Version

Date

Name

Description

Section 14. Appendices

Include any relevant appendices.

(