Production OP
Consider a production line that is to be used for 14 hours per day in order to meet forecasted demand of 1120 units per day. The following precedence diagram with times in seconds describes the tasks necessary to produce this product:
|
|
Line Balancing Worksheet |
|
|||
|
Work Station |
Rem. Time |
Candidates |
Feasible |
Assign |
Idle Time |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
A
B
C
D
E
F
G
34
20
16
10
10
24
38