OPERATIONS MANAGEMENT - PROBLEMS IN - Statistical Quality Control
Chapter 6. Statistical Quality Control
|
Question 1 |
|
|
A quality control manager at a manufacturing facility has taken four samples with four observations each of the diameter of a part.
Samples of Part Diameter in Inches
|
1 |
|
2 |
|
3 |
|
4 |
|
6.2 |
|
5.8 |
|
5.7 |
|
5.8 |
|
6.2 |
|
6.3 |
|
6.1 |
|
6.1 |
|
6.0 |
|
5.9 |
|
6.2 |
|
6.1 |
|
5.9 |
|
5.7 |
|
5.9 |
|
6.2 |
(a) Compute the mean of each sample. (Round answers to 3 decimal places, e.g. 15.250.)
|
Mean of sample 1 |
|
|
|
Mean of sample 2 |
|
|
|
Mean of sample 3 |
|
|
|
Mean of sample 4 |
|
|
(b) Compute an estimate of the mean and standard deviation of the sampling distribution. (Round answers to 4 decimal places, e.g. 15.2500.)
|
Mean |
|
|
|
Standard deviation |
|
|
(c) Develop control limits for 3 standard deviations of the product diameter. (Round answers to 2 decimal places, e.g. 15.25.)
|
CL |
|
|
|
UCL |
|
|
|
LCL |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Question 3 |
|
|
A production manager at a Contour Manufacturing plant has inspected the number of defective plastic molds in five random samples of 35 observations each. Following are the number of defective molds found in each sample:
|
Sample |
|
Number of Defects |
|
Number of Observations in Sample |
|
1 |
|
3 |
|
35 |
|
2 |
|
2 |
|
35 |
|
3 |
|
0 |
|
35 |
|
4 |
|
1 |
|
35 |
|
5 |
|
0 |
|
35 |
|
Total |
|
6 |
|
175 |
Construct a 3-sigma control chart (z = 3) with this information. (If the lower control limit is negative, round the LCL to zero and all other answers to 2 decimal places, e.g. 15.25.)
|
CL |
|
|
|
UCL |
|
|
|
LCL |
|
|
|
Question 4 |
|
|
U-learn University uses a c-chart to monitor student complaints per week. Complaints have been recorded over the past ten weeks. Develop 3-sigma control limits using the following data:
|
Week |
|
Number of Complaints |
|
1 |
|
0 |
|
2 |
|
2 |
|
3 |
|
1 |
|
4 |
|
2 |
|
5 |
|
2 |
|
6 |
|
3 |
|
7 |
|
3 |
|
8 |
|
0 |
|
9 |
|
3 |
|
10 |
|
3 |
(If the lower control limit is negative, round the LCL to zero and all other answers to 2 decimal places, e.g. 15.25.)
|
CL |
|
|
|
UCL |
|
|
|
LCL |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Question 6 |
|
|
Compute the (a) Cpk and (b) Cp measures of process capability for the following machine. (Round answers to 2 decimal places, e.g. 15.25.)
|
Machine data: |
USL = 100 |
|
|
|
LSL = 70 |
|
|
|
Process σ = 5 |
|
|
|
Process μ = 80 |
|
|
Cpk |
|
|
|
Cp |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Question 9 |
|
|
The Crunchy Potato Chip Company packages potato chips in a process designed for 8.0 ounces of chips with an upper specification limit of 8.5 ounces and a lower specification limit of 7.5 ounces. The packaging process results in bags with an average net weight of 7.86 ounces and a standard deviation of 0.1 ounces. The company wants to determine if the process is capable of meeting design specifications. (Round answers to 3 decimal places, e.g. 15.250.)
|
Cp |
|
|
|
Cpk |
|
|
The process is .
|
Question 1 |
|
|
Discuss the key differences between common and assignable causes of variation. Give examples.
|
Question 2 |
|
|
The standard deviation of the distribution of sample means is computed by
|
|
z*σ |
|
|
σ/z |
|
|
σ/x |
|
|
σ/√n |
|
Question 3 |
|
|
For the standard normal distribution, how much confidence is provided within 2 standard deviations above and below the mean?
|
|
97.22% |
|
|
95.44% |
|
|
99.74% |
|
|
99.87% |
|
|
90.00% |
|
Question 4 |
|
|
Six-Sigma quality implies how many average defects per million?
|
|
3.4 |
|
|
6 |
|
|
2600 |
|
|
3σ |
|
|
6σ |
|
Question 5 |
|
|
A control chart for ______________ is used to monitor characteristics that can be measured.
|
|
data |
|
|
attributes |
|
|
variables |
|
|
limits |
|
|
deviations |
|
Question 6 |
|
|
A control chart for ______________ is used to monitor characteristics that have discrete values and can be counted.
|
|
data |
|
|
attributes |
|
|
variables |
|
|
deviations |
|
|
limits |