project management
PROJECT OBJECTIVE
The objective of this project is to have installed a working version of the EHR in production and Test environments with in the next 6 months at cost not to exceed $250,000 with 10-15% recurring maintenance and support cost for useful life of the system.
DELIVERABLES
· Develop specific, measurable goals for EHR
· Assess training needs (computer skills, other)
· Evaluate hardware and networking needs
· Perform workflow analysis
· Evaluate interface and conversion needs
MILESTONES
· Hardware and software installation - Feb 1
· Customized software and configuration – March 8
· Testing of systems and interfaces – May 10
· Chart abstraction and data migration – June - 28
· Training of leadership team, providers, and all staff July - 15
· Mock “go-live” with testing of back-up plans – July – 29
· True GO-Live day Aug - 11
TECHNICAL REQUIREMENTS
· Detailed inventory of printers, faxes, workstations, etc
· New hardware needed and cost
· New network drops
· New Electrical outlets
· Wireless network
· EHR access method (ASP, in house, hosted)
LIMITS AND EXCLUSIONS
· CCHIT and meaningful use criteria are included in the HER
· EHR HIPAA Compliant
· Vendor is responsible for training of staff
· Recurring maintenance and support for useful life of the system
CUSTOMER REVIEW
Elizabeth Baker