Conveyor Belt Project Using MS Project

profileClay1203
conveyor_belt_project_parts_1_and_2.docx

***The first two parts have been completed but are included below for reference purposes***

Project Description

The new computer-controlled conveyor belt is an exciting project that moves and positions items on the conveyor belt within <1 millimeter. The project will produce a new system for future installations, and for replacement of those in the field, at a low cost. The computer-controlled conveyor belt has the potential to be a critical unit in 30 percent of the systems installed in factories. The new system is also easier to update with future technologies.

The Project Priority Matrix for the Conveyor Belt Project (CBP) is:

Time Scope Cost

Constrain X

Enhance X

Accept X

Conveyor Belt Project Assignment

· Enter the first task as "Conveyor Belt Project" and then, enter all the project tasks given in Table A2.11. Indent all project tasks except the first task "Conveyor Belt Project”

· Set the project start date as given

· Set the holidays as given

· Enter the activity time estimates

Use your file from Part 1 and the information provided below to complete this exercise

1. Each work package will represent an activity

2. The project begins January 4, 2010

3. The following holidays are observed: January 1, Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving (4th Thursday in November), December 25th and December 26th

4. If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday, then Monday will be given as a day off

5. The project teams work eight hour days, Monday through Friday

Conveyor Belt Project WBS

Hardware Hardware specifications

Hardware design

Hardware documentation

Prototypes

Order circuit boards

Assemble preproduction models

Operating System Kernel specifications

Drivers

Disk Drivers

Serial I/O drivers

Memory management

Operating system documentation

Network interface

Utilities Utilities specifications

Routine utilities

Complex utilities

Utilities documentation

Shell

System integration Architectural decisions

Integration first phase

System hard/software test

Project documentation

Integration acceptance testing

Table A2.11 (Conveyor Belt Project Schedule)

Activity Description Resource Duration (days) Preceding Activity

1 architectural decisions Design 25 -

2 hardware Development, 50 1

Specifications Design

3 Kernel Design 20 1

specifications

4 Utilities Development, 15 1

Specifications Design

5 Hardware Design, 70 2

design Development

6 Disk drivers Assembly, 100 3

Development

7 Memory Development 90 3

management

8 Operating system Design, 25 3

Documentation Documentation

9 Routine utilities Development 60 4

10 Complex utilities Development 80 4

11 Utilities Documentation, 20 4

Documentation Design

12 Hardware Documentation, 30 5

Documentation Design

13 Integration Assembly, 50 6, 7, 8, 9, 10, 11, 12

First phase Development

14 Prototypes Assembly, 80 13

Development

15 Serial Development 130 13

I/O drivers

16 System Assembly 25 14, 15

Hard/software test

17 Order Purchasing 5 16

Circuit boards

18 Network Development 90 16

interface

19 Shell Development 60 16

20 Project Documentation, 50 16

Documentation Development

21 Assemble Assembly, 30 17F-S, lag 50 days

preproduction Development

models

22 Integrated Assembly, 60 18, 19, 20, 21

Acceptance Development

testing