Define "Critical path", "Slack time", "Resource Levelling" and "Dummy activity" with reference to PERT and CPM.

An architect has been awarded a contract to prepare plans for an urban renewal project. The job consists of the following activities and their estimated value. Draw a critical path arrow diagram for this project, indicate the critical path and calculate the total slack and free slack for each activity.

Job

Description

Predecessor

Expected time in days

A

Prepare preliminary sketches

NA

2

B

Outline specifications

NA

1

C

Prepare drawings

A

3

D

Write specifications

A B

2

E

Run prints

C D

1

F

Have specifications printed

B D

3

G

Assemble bid package

E F

1