Problem
Earned-value analysis. A project budget calls for the following expenditures:
Task Date Budgeted Amount:
Build forms April 1$10,000
Pour foundation April 1$50,000 May 1$100,000
Frame walls May 1$30,000 June 1$30,000
Remaining tasks July 1 and beyond$500,000
Define each term in your own words, calculate these values for the above project, and show your work:
- Budgeted cost baseline (make a graph illustrating this one)
- Budget at completion (BAC)
- Planned value (PV) as of May 1
- Earned value (EV) as of May 1 if the foundation work is only two-thirds complete. Everything else is on schedule.
- SV as of May 1.
- Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May 1.
- Schedule performance index (SPI)
- Cost performance index (CPI)
- Estimate to complete (ETC), assuming that the previous cost variances will not affect future costs
- Estimate at completion (EAC)
4 years ago
10
other Questions(10)
- 5 PAGE APA PAPER DUE IN 24 HOURS
- Course Project -Company Selection is Apple Inc.
- 7 Questions
- NO PLAGIARISM PLEASE, DUE TUESDAY 02/28 BY 6:00PM, PAYING $20.00
- Week1
- If the current population in china is 1.33 billion how many years will it take for the population to reach...
- 1 page help
- Need help on my discussion ASAP
- BUS 430 week 3 discussion 1
- LABORATORY ASSIGNMENT