Nursing Project Management
To complete this Assignment, you will create a Microsoft Project plan for a patient information management system. The primary deliverable for the plan is the patient information management system itself, but it is comprised of many modules. Include the following tasks, subtasks, and timeframes:
- Create the Admission, Discharge, and Transfer Module (requires subtask I, configuration period: 25 days, training period: 10 days)
- Subtask I: Create the Patient Registration Module (requires subtask II, configuration period: 4 days, training period: 4 days)
- Subtask II: Create the Master Patient Index (configuration period: 4 days)
- Subtask III: Create the Patient Scheduling Module (requires subtask II, configuration period: 7 days, training period: 15 days)
9 years ago
15
Answer(1)![blurred-text]()
![]()
Purchase the answer to view it

NOT RATED
- patientinformationmanagementsystem.mpp
- Patientinformationmanagementsystem-1.docx
other Questions(10)
- (Depression)
- Homework - FIN
- Android sample project
- Research paper on History of objected oriented database management system
- Annotated bib
- Business and Society. This is needed as a short post. I would also like whom ever I select to write other parers, because I would like the thinking style to remain the same.
- PCN-521 Week 4 Structural and Experiential Therapist Perspectives Paper
- AF 56 payment link :)
- Assignment 1: Interview Preparation and Discussion(PSY)
- Accounting Questions