35. Manufacturing Easy boy manufactures two types of chairs, Standard and Deluxe. Each Standard chair requires 4 hours to construct and finish, and each Deluxe chair requires 6 hours to construct and finish. Upholstering takes 2 hours for a standard chair and 6 hours for a Deluxe chair. There are 480 hours available each day for construction and finishing and there are 300 hours available per day for upholstering.
a. Write the inequalities that describe the application.
b. Graph the solution of the system of inequalities and identify the corners of the region.
8 years ago
Let x chairs of the Standard type and y chairs of the Deluxe type be produced. ...