Question 1

When completing a forward pass, you carry the early finish to the next activity where it becomes its early start unless the next succeeding activity is a merge activity. In this case you select the smallest early finish number of all its immediate predecessor activities.

A. True

B. False

Question 2

________ activities are to be completed immediately following a particular activity.

A. Parallel
B. Successor
C. Merge
D. Burst
E. Predecessor

Question 3

An activity cannot begin until ALL preceding connected activities have been completed.

A. True

B. False

Question 4

Which of the following correctly calculates the late start for an activity?

A. LF - SL
B. ES - DUR
C. ES – SL