1. Compute the capacity in parts per hour of the following:
a) A station with three machines operating in parallel with 20‐minute process times at each station.
b) A balanced line with single –machine stations, all with average processing times of 15 minutes.
c) A four‐station line with single‐machine stations, where the average processing times are 15, 20, 10, 12 minutes, respectively for stations 1, 2, 3, 4.
d) A four‐station line with multiple‐machine stations, where the number of (parallel) machines at stations 1, 2, 3, 4 is 2, 6, 10, 3 respectively. The average processing times at the stations are 10, 24, 40, 18 minutes, respectively.
e) A three‐station line with ample equipment at all stations (i.e. don’t worry about machines—you only need to make calculations for the labor) staffed by six operators who are identical with regard to average processing times and require 10, 15, 5 minutes, respectively on stations 1, 2, 3.
f) The same line as in part e), except that station 2 now consists of only two parallel machines. Stations 1 and 3 still have ample capacity.
2. Is it possible for a line to have the same throughput with both high WIP and high cycle time or low WIP and low cycle time? Which would you rather have? Why?
7 years ago
60
Purchase the answer to view it

- plagiairismreport.pdf
- Homework1.docx
- Juvenile Justice
- BUS 308 Week 2 Assignment
- psych610_r1_developmental_research_week6 ___TEAM
- Political Science Course Outline
- Are you available?
- project management class
- Week 11 Assignment
- art institute of pittsburgh AA in graphic design ( i only want people that knows about graphic design and the school)
- I
- Drug Therapy